LEED v4 BD+C, EAc1 Enhanced Cx, Option 2. Envelope Cx: Can General Contractor contract for the BECx testing?
NC-v4 EAc1:Enhanced commissioningposted by Theresa Lehman on
Has anyone come across a scenario where the general contractor is required to contract for the functional testing of the building envelope commissioning, where the hired BECx simply "observes" the
Number of spaces
NC-v4.1 LTc8:Electric Vehiclesposted by Norman Sutton on
I have a site with 124 parking spaces. For Option 1 the math points to needing 6.2 spaces (.05 x 124). To earn the credit, will chagring stations for 6 spaces be enough, or will 7
Taking account for thermal brigdingt of construction joints/egde
NC-v4 EAp2:Minimum energy performanceposted by Sonja Kildishev on
I wonder if/how thermal bridging of joints/egde between constructions should be included in the U-value of the construction?
Additional minimum requirement
Data-Centers-NC-v4.1 EAp2:Minimum Energy Performanceposted by Luis Andrade on
Hi everyone,
Quality Views Analysis Results is AutoCase
Pilot-Credits INpc113:Informing Design Using Triple Bottom Line Analysisposted by Mansoureh Jalali on
When I try to add my Views study results to AutoCase it asks for the type of view for both baseline and proposed design.
IAQ Calculator Space Categories
NC-v4 EQp1:Minimum indoor air quality performanceposted by Junaid Mujahid on
In some of our projects, we are providing outdoor air to some spaces which do not require outdoor air supply as per ASHRAE 62.1. For example, water tank room, some storages etc.
Should MAHUs be included in IAQ Calculator
NC-v4 EQp1:Minimum indoor air quality performanceposted by Junaid Mujahid on
In a Mall project, it has multiple kitchens/restaurants which have ecology units that exhaust air (fume hoods).
Partially designed HVAC system
CS-v4 EAp2:Minimum energy performanceposted by Junaid Mujahid on
I'm creating a PRM energy model for a Mall project which is a Core & Shell project in LEED v4.
Regarding discrepancy in wall area for Baseline Model WWR<=40%
NC-v4 EAp2:Minimum energy performanceposted by Anurag Ghosh on
Hello,
We have modelled(proposed) a complex railway station having different wall areas on all the 4 sides of the structure. The simulated report provides the WWR of 47%.