EA P2 and EA C1 requirements clarifications

NC-2009 EAc1:Optimize Energy Performance
posted by  BABAR MEHMOOD  on 

in EA P2, it's written to comply with mandatory provisions which are for example 5.4 which is related to Building envelope under Option 1.

6
Tue Mar 19, 2013, 3:03 pm

Green Wall

CS-2009 EAp2:Minimum Energy Performance
posted by  Yoyo Shek  on 

Does anyone have idea if we could model the benefit of using green wall (Vegetated)?

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Mar 19, 2013, 4:06 am

Exception For Baseline HVAC System

CS-2009 EAp2:Minimum Energy Performance
posted by  Yoyo Shek  on 

I am running a high-rise commercial development for LEED-CS. According to Table G3.1.1B, the baseline system shall be chilled water.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Mar 19, 2013, 2:51 am

Question regarding the OPR and BOD

CI-2009 EAc2:Enhanced Commissioning
posted by  Robert Calloway  on 

We have a client that has the Owners Project Requirements (OPR) but no Basis of Design (BOD). Is it acceptable for the OPR to be used in place of the BOD?

2
Mon Mar 18, 2013, 7:48 pm

Site boundary for a project mixing Leed & non Leed new buildings

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  serge sidoroff  on 

Is it possible to submit to the Leed certification only one of two adjacent new buildings, an office building and an industrial plant ?

4
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Mar 18, 2013, 6:21 pm

Building controls

CS-2009 EAp2:Minimum Energy Performance
posted by  FABIO VIERO  on 

Hello all, Two little questions: 1) If I had automatic internal draps, would I be obliged to simulate them in the baseline/proposed building? 2) Is it possible to consider, as for the lighting sys

3
Head of Sustainability
Manens S.p.A.
LEEDuser Premium Member
16 thumbs up
Mon Mar 18, 2013, 5:00 pm

LEED project boundary in underground garage

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Michael Haugeneder  on 

Hello everyone, we're facing a complex situation with regard to the determination of our LEED project boundary.

6
Default Avatar
Sustainability Consultancy Services
Cushman & Wakefield
LEEDuser Basic Member
11 thumbs up
Mon Mar 18, 2013, 2:46 pm

CHP biofuel certifications

CS-2009 EAc2:On-site Renewable Energy
posted by  Marcello Polverino  on 

Hi LEED-User, I would like to know which documents I need to provide to the USGBC for a block heat and power plant fueled with biogas? Thanks Best wishes from Hanover (germany)

6
Fri Mar 15, 2013, 1:11 pm

Energy Modeling for an outdoor shopping mall

CS-2009 EAp2:Minimum Energy Performance
posted by  LEED Pro Consultant  on 

Hello!! I have a question regarding energy modeling for my project located in Northeast Mexico. It is a shopping mall in which all the middle hallways and circulation areas are going to be outdoor,

3
Fri Mar 15, 2013, 12:46 am

R values

NC-2009 EAp2:Minimum Energy Performance
posted by  Robert Sutton  on 

It is true that the R values in 90.1 have to be used as a minimum in the performance rating calculations? Using tables and materials description sets the basis for your baseline model?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Mar 14, 2013, 4:47 pm