Process energy? Exhaust Fan to relieve electric transformer heat

NC-2009 EAp2:Minimum energy performance
posted by  Matt Scott  on 

Our project has several spaces with electric transformers where we are using an exhaust fan and an outside air louver to relieve the heat loss from the transformer.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Tue Aug 13, 2013, 6:39 pm

Regional Material Tracking with Multiple Forms of Transportation

NC-2009 MRc5:Regional materials
posted by  Karleigh Pihowich  on 

I have a material that was extracted 425 km from the manufacture point and transported by truck. After manufacture the material was shipped via rail to the project site which is 2076 km.

2
Default Avatar
LEEDuser Premium Member
1 thumbs up
Tue Aug 13, 2013, 5:56 pm

Demolition implemented by separate contractor

CS-2009 MRc2:Construction waste management
posted by  Morteza Kasmaei  on 

This CS project is a major renovation to an existing building and has separate contractors for demolition and major construction.

4
Default Avatar
LEEDuser Expert
472 thumbs up
Tue Aug 13, 2013, 5:33 pm

Two methods: T-stats and windows in the same project?

CS-2009 IEQc6:Controllability of systems - thermal comfort
posted by  Diana Nezamutinova  on 

Would a mechanically ventilated building be able to rely on 2 methods for documenting compliance: T-stats and windows? Some occupants will use one, while the others will rely on another.

2
Tue Aug 13, 2013, 9:53 am

SSc7.2 Weighted Average Calculator

NC-2009 SSc7.2:Heat island effect - roof
posted by  Gabriel Moreno  on 

Apologies if this question has already been answered - but I've searched as thoroughly as possible and did not find a satisfiable explanation. I am running a simple test with the following values;

8
Default Avatar
Sustainability Architect
LEEDuser Basic Member
88 thumbs up
Mon Aug 12, 2013, 11:19 pm

Kitchen Efficient Equipments

NC-2009 EAp2:Minimum energy performance
posted by  Marina Andrade  on 

Hi! How can i gain points in my simulation with kitchen equipments? I'm working on a project that has automation and i don't know how can i indicate this. I think all kitchen equipments will be

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Mon Aug 12, 2013, 7:01 pm

Occupancy Sensor and/or Decorative lighting credit

CI-2009 EAp2:Minimum energy performance
posted by  Saju Varghese  on 

Could occupancy sensor credit under G.3.2 be used towards meeting the 10% lighting savings requirement? Could credit for decorative lighting be implemented as well 9.6.2a?

6
Mon Aug 12, 2013, 6:48 pm

ATM Machine

NC-2009 SSc2:Development density and community connectivity
posted by  Wei Jiang  on 

Would anyone consider ATM machine as one of the basic services (Banks), for Option 2 - community connectivity?

3
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Mon Aug 12, 2013, 5:34 pm

Rainwater storage system

EBOM-2009 WEc3:Water efficient landscaping
posted by  Karin Wohlert  on 

I'm looking for a calculator or guide that would suggest how much rainwater could be collected in Mid-summer or the month with the highest irrigation demand.

3
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Mon Aug 12, 2013, 4:34 pm

Predominant spaces determined by square footage or hours of use?

NC-2009 EAp2:Minimum energy performance
posted by  Matt Scott  on 

I have a roughly 48,000 sf church with the following breakdown by area and hours of use: 1st Floor: 4,100 sf Multipurpose Space used 16 hours per week 8,200 sf Common Space used 72 hours per week

6
Default Avatar
Engineer
N.E. Fisher & Associates, Inc.
LEEDuser Basic Member
12 thumbs up
Mon Aug 12, 2013, 3:25 pm