Forum quick links
Plan development
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Michael E. Edmonds-Bauer on
For this purpose we would like to know if: - In order to comply with requirements, can we develop a plan similar to the one use for the core & base building (calibrated simulation)?
Alternative Compliance Path for SRI compliant products
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Maya Karkour on
Dear All, I received an email from LEEDUser called "LEED Updates: New Interpretations & Addenda" One interesting point was the following: "USGBC introduces multiple new options for non-U.S.
Green power & onsite solar
CI-2009 EAc4:Green Powerposted by Stacey Olson on
We have a project where onsite solar panels generate a portion of the electricity serving the building - but not all.
R-value of total window assembly for energy model
NC-2009 EAc1:Optimize Energy Performanceposted by Michelle Lambert on
In our project's LEED design submission, the engineer used the R-value of the glazing in the energy model.
District cooling PV array
NC-2009 EAc2:On-Site Renewable Energyposted by Katherine Ann Resurreccion on
If the project is district cooled with option 1 where the cooling energy consumption is determined by adding chilled water meter in the energy model for EAc1, in calculating the capacity of the PV
CS eligibility for industrial condos
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by nancy picard on
Is the following building eligible for a CS certification: Basically a big 205 000 sqft box with no common areas, with 30 000 sqft of mezzanine for future office space.
VRF Outdoor Fan Motor - Electric Efficiency
NC-2009 EAp2:Minimum Energy Performanceposted by María Fernanda Aguirre on
Hi!
Two buildings connected with the same HVAC system
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
I’m going to model two buildings that are on the same site and are of the same owner. The owner wants to achieve the LEED certification for both. The buildings aren’t attached, i.e.
District / Campus Energy - Modeling Option 2 (Full accounting)
NC-2009 EAp2:Minimum Energy Performanceposted by Maya Karkour on
Dear All, I am intending to model a building on campus which is connected to a campus energy system providing chilled water and hot water.
WE p1 requirement for Industrial shell building
CS-2009 WEp1:Water Use Reductionposted by Karl Heitman on
We are working on a speculative 1,000,000 SF industrial warehouse which is pursuing a LEED CS.