Multi-Flow Showerhead

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Annalise Reichert  on 

I am working on a project that plans to install a shower head with three flow options: 0.5 GPM-1.0 GPM -1.5 GPM. How do we account for multi-flow showerheads on the WEp1 form?

1
Wed Mar 2, 2016, 10:14 pm

Shared underground parking with non LEED certified buildings

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Jorge Lopez de Obeso  on 

Our project, a 200,000 sqft CS office tower (much more to the 20% of the total area) shares 3 levels of underground parking lot with two other buildings (Movie theater, shops, restaurants).

0

Towers as part of a single building

NC-v4 EAp2:Minimum energy performance
posted by  Francesco Passerini  on 

A building is composed by three towers that have the basement, the ground floor, and the first floor in common. The system for the baseline model shall be System 8.

1
Thu Mar 3, 2016, 3:33 pm

Project Boundary

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Antje Holdefleiss  on 

Hello Everyone I have the following questions regarding the LEED Project boundary: · Are the project boundary only referring to the ground floor?

1
Wed Mar 16, 2016, 6:56 pm

Glass Demo

NC-2009 MRc2:Construction Waste Management
posted by  Donald Green  on 

Has anyone had any luck recycling glass taken from a commercial building? They are double pane commercial units removed from the curtainwall system.

1
Thu Mar 3, 2016, 4:10 pm

WEc1 - We don't really have a "SITE" outside of the building env

Retail-NC-v2009 WEc1:Water efficient landscaping
posted by  Lou Niles II  on 

Hello I am working on Two Separate projects that actually overlap on a site; they are not registered as Master Site or Campus and we don't want that at this time. Project A Surrounds Projects B. Pr

1
Sat Aug 26, 2017, 11:54 pm

Existing Lighting in a TI

CI-2009 EAp2:Minimum Energy Performance
posted by  Annalise Reichert  on 

I am working on a TI retrofit project that did not replace any existing lighting in their space due to budget constraints.

1
Thu Mar 3, 2016, 9:27 pm

Painting/coating in tenant space

CS-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Indochine Engineering VN  on 

Hi, My project is a mixed use building with 2 floor on the top for apartments. building developer design interior fit out in all apartment for lease.

1
Thu Jan 19, 2017, 10:50 am

Pursing credit in an existing building

Pilot-Credits EQpc78:Design for active occupants
posted by  Dee Spiro  on 

Our project involves renovating an existing building on a university campus.

0

Implementing on a university campus

Pilot-Credits PC14:Walkable Streets
posted by  Dee Spiro  on 

When I searched the forum for insight on how to apply/adapt some of the requirements for a campus setting, the posts were from way back in August 2012.

0