Hello. We will make the Eap2 by Energy Star. To do this we have invoices for the total consumption of the building (offices + CPD), and manual readings consumption of different meters. Is this enough to get the qualifying portfolio or need automated meter to take the differents readings?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $12.95 »
Ben Stanley
Senior Sustainability ManagerWSP - Built Ecology
LEEDuser Expert
250 thumbs up
February 3, 2016 - 11:20 am
Hi Mercé,
The meters do not have to be automated in order to meet EAp2. So long as you have meters that monitor the entire consumption of the building, and those meters are calibrated or owned by the utility, you should be ok.
If you are thinking of pursuing EAc3.2 however, that credit requires that meters are readings are taken automatically. Manual readings do not work for that credit.