Forum quick links
Warehouse -
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Devani PERERA on
Hi, I am working on a warehouse project.
MPR #6 modification
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Ron Dean on
Hello, I've seen in leedonline for a recently registered project I'm working on that this form (PIf1) has been updated from version 4.0 to 5.0.
Measurements
Pilot-Credits EQpc24:Acousticsposted by Anulak Siwabut on
I don't see specified in the documentation the extent of measurements required in order to meet this credit.
Manufacturer specs required or are nameplates sufficient?
EBOM-2009 EAp3:Fundamental Refrigerant Managementposted by Alice Cook on
Are you required to provide the manufacturer's specifications, or is it enough to upload the nameplates to LEED?
Access to Public Spaces
Pilot-Credits PC14:Walkable Streetsposted by Jennifer Preston on
Is there a requirement or guideline as to how far from the project site the public spaces/squares/plazas need to be?
"Submit feedback survey"
Pilot-Credits PC14:Walkable Streetsposted by Jennifer Preston on
Does the "feedback survey" refer to the "Additional Questions" listed on the Bird's Eye View tab? Or is there another survey that this is supposed to be linked to?
Exclude retail?
NC-2009 PIf1:Minimum Program Requirementsposted by Mike D on
Our project has got some retail on the ground floor of an office building that the design team does not want to include in the LEED assessment.
Modify Established Project Boundary?
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Ali Kopyt on
The client for our CI-2009 project has decided to expand their footprint within the existing building to include more office spaces.
SS 4.3
Healthcare-v2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Marina Andrade on
Our project is an hospital and the municipal code requires that places that generate traffic, like hospitals, they must have motorcycle parkings too, not only parking capacity for cars, we have to
Gross Floor Area, Mechanical Space
NC-2009 PIf2:Project Summary Detailsposted by Gary Ashford on
ASHRAE is not specific about deducting for floor openings. For cost estimating and code review, we normally deduct elevator shafts and stairwells.