Wood waste to be recycled into biomass fuel

NC-2009 MRc2:Construction Waste Management
posted by  Noriko Nagazumi  on 

Hi, Our project emits a certain volume of wood waste, which is used mainly for packaging equipment.

1
Thu Jun 6, 2013, 3:49 pm

ASHRAE/IECC Compliance for AHU's, RTU's and Heat Pumps

NC-2009 EAc3:Enhanced Commissioning
posted by  Peter Dishno  on 

Hello Design Review Experts, During a design review for a residential high rise, we noted that several areas of common space did not seem to have the capacity to use an economizer, Demand Control

1
Fri Jun 7, 2013, 2:21 pm

Use of EA Cr 6 for a CS Project

EBOM-2009 EAc6:Emissions Reduction Reporting
posted by  emily reese moody  on 

Hi, I'm wondering if anyone has tried attempting this credit as an ID strategy in a CS project.

1
Thu Nov 7, 2013, 9:20 pm

translucent privacy glazing & EQc8.1 / 8.2

CI-2009 IEQc8.1:Daylight and Views—Daylight
posted by  John Steingraeber  on 

We are pursuing LEED CI certification for a client who has requested the application of translucent window film in some spaces for security concerns.

1
Mon Jun 10, 2013, 12:24 pm

On Site Renewable

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Joseph Snider  on 

The project would like to consider this credit. For that a PV system was previously installed and has been in operation within the performance period.

1
Fri Aug 30, 2013, 3:44 pm

water efficiency review

NC-2009 WEc3:Water Use Reduction
posted by  Shristi Bajracharya  on 

When we sent the WE credit for review for our project, we sent a water use calculation stating that the potable water usage in the project has been reduced by 43% from a calculated baseline design.

1
Mon Jun 10, 2013, 5:35 pm

Preferred parking in master site project

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Lolita Wu  on 

We are working on a master site with three buildings in the block. Two office buildings are pursuing LEED CS and a hotel building is pursuing LEED NC.

1
Sun Nov 3, 2013, 2:19 am

50% of material purchase & composite panel question

EBOM-2009 MRc3:Sustainable Purchasing—Facility Alterations and Additions
posted by  Karin Wohlert  on 

Achieve sustainable purchases of 50% of total purchases (by cost) during the performance period.

1
Wed Jul 31, 2013, 4:05 pm

Views and Interstitial blinds

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Sean Hogan  on 

Hi, I'm working on a project where south, east and west elevations will have twin skin glazing with interstitial blinds.

1
Tue Jun 11, 2013, 3:33 pm

Can we go for enhanced commissioning after start of operation

NC-2009 EAc3:Enhanced Commissioning
posted by  Abdulrahman Sherazy  on 

Our client have decided suddenly to go for enhanced commissioning. The construction is complete and the building starts to operate. The fundamental commissioning has been already done.

1
Tue Jun 11, 2013, 6:17 pm