Hi, Our project emits a certain volume of wood waste, which is used mainly for packaging equipment.
ASHRAE/IECC Compliance for AHU's, RTU's and Heat Pumps
NC-2009 EAc3:Enhanced Commissioningposted by Peter Dishno on
Hello Design Review Experts, During a design review for a residential high rise, we noted that several areas of common space did not seem to have the capacity to use an economizer, Demand Control
Use of EA Cr 6 for a CS Project
EBOM-2009 EAc6:Emissions Reduction Reportingposted by emily reese moody on
Hi, I'm wondering if anyone has tried attempting this credit as an ID strategy in a CS project.
translucent privacy glazing & EQc8.1 / 8.2
CI-2009 IEQc8.1:Daylight and Views—Daylightposted by John Steingraeber on
We are pursuing LEED CI certification for a client who has requested the application of translucent window film in some spaces for security concerns.
On Site Renewable
EBOM-2009 EAc4:On-Site and Off-Site Renewable Energyposted by Joseph Snider on
The project would like to consider this credit. For that a PV system was previously installed and has been in operation within the performance period.
water efficiency review
NC-2009 WEc3:Water Use Reductionposted by Shristi Bajracharya on
When we sent the WE credit for review for our project, we sent a water use calculation stating that the potable water usage in the project has been reduced by 43% from a calculated baseline design.
Preferred parking in master site project
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Lolita Wu on
We are working on a master site with three buildings in the block. Two office buildings are pursuing LEED CS and a hotel building is pursuing LEED NC.
50% of material purchase & composite panel question
EBOM-2009 MRc3:Sustainable Purchasing—Facility Alterations and Additionsposted by Karin Wohlert on
Achieve sustainable purchases of 50% of total purchases (by cost) during the performance period.
Views and Interstitial blinds
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by Sean Hogan on
Hi, I'm working on a project where south, east and west elevations will have twin skin glazing with interstitial blinds.
Can we go for enhanced commissioning after start of operation
NC-2009 EAc3:Enhanced Commissioningposted by Abdulrahman Sherazy on
Our client have decided suddenly to go for enhanced commissioning. The construction is complete and the building starts to operate. The fundamental commissioning has been already done.