SSp2 Environmental SIte Assessment (LEED Healthcare)

Healthcare-v2009 SSp2:Environmental site assessment
posted by  Lesley Treacy  on 

Hi, I am working on the LEED aspects of a healthcare project in KSA. A full and detailed EIA Study for the project was completed to local standards and no contaimination was found.

1
Mon Oct 22, 2012, 7:00 pm

Further normalized EUI

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  SENGATHIR SELVAN  on 

Hi there, in our efforts to achieve LEED EBOM certification for a production facility (garment washing plant) in Dhaka, we have implemented energy conservation measures.

1
Thu Oct 25, 2012, 3:23 pm

Fan's power

CS-2009 EAp2:Minimum Energy Performance
posted by  Michela Tedeschi  on 

Hello all, two little questions about fan's power: - Which is exactly the difference between demand fan power, peak fan power and fan power allowance? - How do i have to relate baseline and propose

1
Mon Oct 22, 2012, 2:33 pm

Landscape Factors for Baseline Case

CS-2009 WEc1:Water Efficient Landscaping
posted by  Oliver Lange  on 

I would like to know, where I can find a good source for the specific landscape factors (species-, density- and microclimate factor) of plants for the calculations in the baseline case. Is it even

1
Wed Dec 5, 2012, 5:10 pm

EER requirement and VFD air cooled equipment - Help

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Tiombe Parrish  on 

We have a proposed LEED Silver office building under LEED 2009 for Commercial Interiors.

1
Thu Oct 25, 2012, 1:49 pm

Materials Which Always Get Review Comments

NC-2009 MRc4:Recycled Content
posted by  Hernando Miranda  on 

It is obvious that the LEED reviewers use a set of predetermined comments for certain material claims made.

0

SF used for energy model vs. building GSF

NC-2009 EAp2:Minimum Energy Performance
posted by  Craig Flandermeyer  on 

Our building energy model s.f.(table eap2-1) 74,000+/- does not match the gross building s.f. reported in 1.1A 94,000+/-. The difference is approximately 20,000 s.f.

1
Mon Oct 22, 2012, 11:36 pm

Choosing Baseline HVAC-System in climate zone 1b

NC-2009 EAc1:Optimize Energy Performance
posted by  Johannes Hopf  on 

Hi, 90.1-2007 confuses me a little. Our project (4 story, 9000 m²/90000 ft²) is located in climate zone 1b. The proposed building is heated by an electrical heatpump.

1
Tue Oct 23, 2012, 1:43 pm

Major Renvation Baseline Building Envelope Selection for Title 2

NC-2009 EAc1:Optimize Energy Performance
posted by  Jayme Buresh  on 

Hi, I know that Appendix G states that if the envelope of a building is renovated, then the existing envelope construction is used for the baseline.

0

ESC plan implemented after or at the commencement of excavation?

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Valentin Grimaud  on 

Hi All, we are wondering if the general contractor should implement the ESC at the same time of the leveling and excavation works begin, or if it could done after?

1
Fri Nov 23, 2012, 3:54 am