Forum quick links
Process Loads Description
CI-2009 EAc3:Measurement and Verificationposted by Saju Varghese on
Im trying to find out what would be considered process loads to be metere separately, is there a definition from LEED?
Energy Cost broken out in Lease
CI-2009 EAc3:Measurement and Verificationposted by Sadie Martin on
Hi, we are working on getting the verbiage of the lease correct.
ACP using v4 language
CI-2009 EAc3:Measurement and Verificationposted by Brightworks Sustainability on
LI #10418 allows LEED-NC v2009 projects to meeting the M&V credit by meeting LEED v4 enhanced commissioning, monitoring-based commissioning, and the advanced energy metering credit.
compressed air
CI-2009 EAc3:Measurement and Verificationposted by Adrienn Gelesz on
I have a manufacturing plant extension CI project were compressed air is entering the LEED space from the non-CI parts of the building. (
To meter or not to meter
CI-2009 EAc3:Measurement and Verificationposted by Rudolph Carneiro on
I have a store (case 1) with a small 60 ton chiller, 2 AHU's, lighting, and plug loads. If HVAC, plug loads, and lighting can be measured on one meter, how many meters do I need?
BTU Metering for Existing HVAC
CI-2009 EAc3:Measurement and Verificationposted by Jareb Ketay on
I have a tenant renovation project occupying 1 story of an existing 10 story building (
Case 1 Option 2
CI-2009 EAc3:Measurement and Verificationposted by breeze glazer on
We have a situation where the tenant space, is within a building owned, by the owner.
case 1, however what happens if space will be owned
CI-2009 EAc3:Measurement and Verificationposted by Courtney Royal on
for example, the project is a large building with a commercial spaces on each floor that will be sold.
M&V case 2
CI-2009 EAc3:Measurement and Verificationposted by Chris Miller on
CI project, 75% or more of the space is occupied by the tenant, and I have seen the 4/1/12 addenda with the replacement language for Case 2.