Process Loads Description

CI-2009 EAc3:Measurement and Verification
posted by  Saju Varghese  on 

Im trying to find out what would be considered process loads to be metere separately, is there a definition from LEED?

1
Thu Apr 18, 2013, 10:38 pm

Energy Cost broken out in Lease

CI-2009 EAc3:Measurement and Verification
posted by  Sadie Martin  on 

Hi, we are working on getting the verbiage of the lease correct.

1
Fri Nov 28, 2014, 9:44 pm

ACP using v4 language

CI-2009 EAc3:Measurement and Verification
posted by  Brightworks Sustainability  on 

LI #10418 allows LEED-NC v2009 projects to meeting the M&V credit by meeting LEED v4 enhanced commissioning, monitoring-based commissioning, and the advanced energy metering credit.

1
Wed Oct 5, 2016, 6:40 pm

compressed air

CI-2009 EAc3:Measurement and Verification
posted by  Adrienn Gelesz  on 

I have a manufacturing plant extension CI project were compressed air is entering the LEED space from the non-CI parts of the building. (

1
Fri Sep 13, 2013, 8:55 pm

To meter or not to meter

CI-2009 EAc3:Measurement and Verification
posted by  Rudolph Carneiro  on 

I have a store (case 1) with a small 60 ton chiller, 2 AHU's, lighting, and plug loads. If HVAC, plug loads, and lighting can be measured on one meter, how many meters do I need?

1
Mon Nov 26, 2012, 4:45 pm

Metering

posted by  John Bauer  on 
1
Tue Jun 22, 2010, 11:04 pm

BTU Metering for Existing HVAC

CI-2009 EAc3:Measurement and Verification
posted by  Jareb Ketay  on 

I have a tenant renovation project occupying 1 story of an existing 10 story building (

1
Tue Sep 23, 2014, 7:13 pm

Case 1 Option 2

CI-2009 EAc3:Measurement and Verification
posted by  breeze glazer  on 

We have a situation where the tenant space, is within a building owned, by the owner.

1
Thu May 26, 2011, 11:12 pm

case 1, however what happens if space will be owned

CI-2009 EAc3:Measurement and Verification
posted by  Courtney Royal  on 

for example, the project is a large building with a commercial spaces on each floor that will be sold.

1
Tue Apr 14, 2015, 2:46 pm

M&V case 2

CI-2009 EAc3:Measurement and Verification
posted by  Chris Miller  on 

CI project, 75% or more of the space is occupied by the tenant, and I have seen the 4/1/12 addenda with the replacement language for Case 2.

1
Tue Jan 7, 2014, 8:19 pm