CI-2009 EAc3:Measurement and Verificationposted by Leticia SooHoo on
Hello, we are doing a LEED CI project for a large tenant occupying multiple floors. We will pursue Case 1 (less than 75% of area) - submetering.
submetering equipment
CI-2009 EAc3:Measurement and Verificationposted by Yaser Al Sharif on
our Project is LEED CI v3 at credit EA c3, what is process uses ( electric) and process uses (fuel) ?????? another question , at our tenant space we have boiler fuel operated to supply under floor
Case 2: Meter base building/ Submetering tenant space
CI-2009 EAc3:Measurement and Verificationposted by Susan M. Kaplan on
This might be a redundant question; I'm sorry if it is. We fall into the Case 2 category as we're more than 75% of the building.
Are Form submetering requirements greater than Ref Guide?
CI-2009 EAc3:Measurement and Verificationposted by Raphael Sperry on
In Case 1 (project
Emergency generator fule meter
CI-2009 EAc3:Measurement and Verificationposted by Edwin Wealend on
Hi we have a LEED CI project that is served by an emergency back-up generator that serves multiple floors. Is it really a requirement to meter emergency back-up generator fuel?
Tenant Sub-Metering
CI-2009 EAc3:Measurement and Verificationposted by Donald Green on
Our tenant will have sub-meters installed on the lighting and HVAC electrical panels on each floor of their tenant space.
Tenant Submetering
CI-2009 EAc3:Measurement and Verificationposted by sompoche sirichote on
I have read the previous threads but still not sure about the tenant submetering. The Table 2 in LEED CI guideline indicates that no submeter is required for the cooling if it is included in prora
initial cost for lease
CI-2009 EAc3:Measurement and Verificationposted by Monica Hue on
Is there are is an initial fee that must be paid upfront when the tenant signs the lease to pay for energy use? If there is this fee, how much does that typically cost?
M&V- energy costs paid by tenant
CI-2009 EAc3:Measurement and Verificationposted by Sarah Marvez on
Our project occupies