CI-2009 EAc2:Enhanced Commissioning
posted by  Akos Brandecker  on 

Does the seasonal commissioning have to be done by the same CxA who does all other commissioning activities or can a separate party be contracted for this? Any thoughts?

5
Director of Sustainability
Living Building Consultancy
LEEDuser Basic Member
6 thumbs up
Wed Jul 23, 2014, 5:07 pm

applying for the Certification before or after the 10 months

CI-2009 EAc2:Enhanced Commissioning
posted by  Carolina Vergnano  on 

My doubt is if it´s possible to Certificate a building with the Operation and Maintenance Manual made by the CxA, or if it´s needed to wait the 10 months required for the Enhanced Commissioning. Wo

6
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri May 30, 2014, 1:13 am
2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Mon Jul 15, 2013, 8:05 pm

EAc2 Submission Requirements

CI-2009 EAc2:Enhanced Commissioning
posted by  John Steingraeber  on 

I am very interested in pursuing LEED CI certification for a buildout of my firm's offices. This will be my/our first LEED project.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Jun 11, 2013, 9:39 pm

Fundamental and Enhanced Commissioner

CI-2009 EAc2:Enhanced Commissioning
posted by  Susan F.  on 

We have a project that is about 125,000 sf and are working with a consultant that is developing the OPR with the client and also writing the BOD for the project.

2
Thu Jun 6, 2013, 7:01 pm

Question regarding the OPR and BOD

CI-2009 EAc2:Enhanced Commissioning
posted by  Robert Calloway  on 

We have a client that has the Owners Project Requirements (OPR) but no Basis of Design (BOD). Is it acceptable for the OPR to be used in place of the BOD?

2
Mon Mar 18, 2013, 7:48 pm

Systems Manual

CI-2009 EAc2:Enhanced Commissioning
posted by  Frank Weiss  on 

I was envisioning the Systems Manual to be an O&M manual with drawings, equipment manuals etc. Upon GBCI review we received the comments shown below.

4
Thu Dec 6, 2012, 2:04 pm

Enhanced Commissioning Action Steps

CI-2009 EAc2:Enhanced Commissioning
posted by  Garrett Billings  on 

We are afraid we will get denied out submittal for enhanced commissioning because we didn't follow the process step-by-step as defined above in the "Action Steps".

5
Default Avatar
Project Manager
Jones Lang LaSalle
LEEDuser Basic Member
18 thumbs up
Thu Oct 20, 2011, 3:47 pm