Scope of EAp2 we must include to meet the compliance

CI-2009 EAp2:Minimum Energy Performance
posted by  Takayuki Hirota  on 

We are planning to renovate an existing building which is used as an office, aiming for LEED CI certification.

6
Wed Feb 19, 2014, 11:22 am

Relocated UPS

CI-2009 EAp2:Minimum Energy Performance
posted by  Gaston Michaud  on 

We are currently working on a project that includes a 120 kVA UPS that is not Energy Star rated. This equipment was brought from another facility; should we include this in our EAp2 calculations?

3
Wed Jan 15, 2014, 9:22 pm

LEED CI EAp2 - ASHRAE 90.1 building envelope compliance

CI-2009 EAp2:Minimum Energy Performance
posted by  Michele Helou  on 

Can anyone tell me if the addition of interior storm windows without a change in existing fixed windows would trigger having to meet either the prescriptive requirements or the ECB ch.

3
Principal
Sage Design & Consulting
LEEDuser Basic Member
55 thumbs up
Fri Dec 6, 2013, 4:21 pm

ENERGY STAR equipment in medical clinic finish-out

CI-2009 EAp2:Minimum Energy Performance
posted by  Christine Robbins-Elrod  on 

Our LEED-CI project is fitting within a shell space of a much larger LEED-NC hospital project (while the hospital also owns the clinic that is pursuing LEED-CI, GBCI has already confirmed that LEED

4
Tue Nov 19, 2013, 8:14 pm

EAp2 and EAc1.3

CI-2009 EAp2:Minimum Energy Performance
posted by  Kalyan Nishtala  on 

Hi, I am new to LEED CI and am confused about a couple of things.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Sep 23, 2013, 7:44 pm

Occupancy Sensor and/or Decorative lighting credit

CI-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

Could occupancy sensor credit under G.3.2 be used towards meeting the 10% lighting savings requirement? Could credit for decorative lighting be implemented as well 9.6.2a?

6
Mon Aug 12, 2013, 6:48 pm

Minimum Reqs

CI-2009 EAp2:Minimum Energy Performance
posted by  John-David Hutchison, LEED AP BD+C, PMP  on 

We are preparing for an 4800 sq ft office renovation in a portion three story building and would like to pusue LEED-CI. We will not be touching the HVAC systems; large rooftop units.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Jul 29, 2013, 5:19 pm

Too early to determine the EnergyStar equipment

CI-2009 EAp2:Minimum Energy Performance
posted by  R Jones  on 

Our CI project won't be occupied until 2015 and the IT and AV equipment schedules aren't yet detailed, just an outline of the power demands for the M&E design is available.

3
Default Avatar
LEEDuser Premium Member
60 thumbs up
Thu Jul 25, 2013, 2:51 pm

HVAC to meet COP, outside US

CI-2009 EAp2:Minimum Energy Performance
posted by  SW LEE  on 

Hi, We have a project outside US. Our AC unit able to meet stated EER in ASHRAE 90.1, but is not ARI tested.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu May 23, 2013, 6:42 am

EA Minimum Energy Performance - Star Rated Equipment

CI-2009 EAp2:Minimum Energy Performance
posted by  Anya Benkabbou  on 

Could an EPEAT Gold Cert equipment be considered equivalent to Energy Star qualified? Really appreciate clarification with this.

3
Associate
Ponte Mellor Architects, Ltd
LEEDuser Basic Member
0 thumbs up
Mon Apr 29, 2013, 7:15 pm