Forum discussion

CI-2009 EAp2:Minimum Energy Performance

EAp2 and EAc1.3

Hi, I am new to LEED CI and am confused about a couple of things. Is it allowed to choose to meet the requirements of section 11 through an energy model for the prerequisite and use option 1 for EAc1.3 or should an energy model be used for both the prerequisite and the credit? Our plan is to use an energy model for the prerequisite since we are the design team and will put together a model for load estimates and use option 1 for the credit since we are not sure if we can achieve 30% savings which seems like a tall order for a CI project. Thanks a lot!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 09/23/2013 - 19:34

You do not have to use the model created for EAp2 in the pursuit of EAc1.3. You can pursue option 1 for that credit.

Mon, 09/23/2013 - 19:44

Thanks Marcus!

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.