CI-2009 WEc1:Water use reductionposted by Garrison Elder on
I am a little confused by what i have read concerning WEp1 and what fixtures are being used by a tenant vs what is in the scope. I have a CS poject where I will acheive 32% water savings.
Locker Rooms
CI-2009 WEc1:Water use reductionposted by Graham Langton on
I have faucets in a locker / changing room. Reading the credit language it doesn't explicitly state that they should / shouldn't be included? Any Idea?
Sensor Type Flush Fixtures
CI-2009 WEc1:Water use reductionposted by Katherine Ann Resurreccion on
Hi Would Sensor activated flush fixtures like urinals and WCs have the same flow rate calulations as a sensor type flow fixture? Would it follow the default 12sec / 60 cycle?
Hybrid Urinals
CI-2009 WEc1:Water use reductionposted by Nilda De Coutte on
Hi, I would like to know if anyone has any information (case study, formal review, experience with) of any of the hybrid urinals currently available in the market.
Base building fixtures meet old LEED 2.0, but not LEED CI 2009
CI-2009 WEc1:Water use reductionposted by Sandra Eremic on
Our project occupies (4) out of (10) floors of a building which was LEED 2.0 certified. We are attempting Silver under LEED CI 2009.
Toilets not within the tenant space
CI-2009 WEc1:Water use reductionposted by Mike D on
For WE Prerequisite 1 and WE credit 1, should toilets that are not within the tenant space be included in the calculations? If not, how do we complete the online form as it marks incomplete when th
WATER USE REDUCTION
CI-2009 WEc1:Water use reductionposted by sajeev john on
DOES THE COMMON TOILEST IN A FLOOR COME UNDER TENANT SCOPE? ENTIRE FLOOR IS OCUPIED BY SAME COMPANY? FLOOR IS MEANT TO BE RENT TO DIFFERENT TENANATS AND OUR COMPANY IS OCCUPYING THE ENTIRE FLOOR?
Existing Blow-out toilets
CI-2009 WEc1:Water use reductionposted by Russell Philstrom on
Our project is in a 57-story building where the existing toilets are original to the building (1972) and are blow-out toilets at 3.5gpf.
LEED Retail CI customer and FTE calculations
CI-2009 WEc1:Water use reductionposted by Jeanne Varney on
For LEED Retail CI, to calculate the WEc1 water reduction you have to input the number of FTE's as well as customers.
WEc1: Only one fixture in CI Space
CI-2009 WEc1:Water use reductionposted by Susan Di Giulio on
Dear Tristan, If you only have one fixture, a faucet in staff lunchroom, in a CI project, and it does meet the goal of 20% better than code, i.e. 1.5 gpm. Then do you gain this credit?