Query for Minimum Energy Performance
EBOM-2009 EAc1:Optimize Energy Performanceposted by Manasi Kulkarni on
Our project is a Mall Building wherein the Owner of the Mall is trying for certification. There are 100's of retailers occupying the building.
Golf Course Clubhouse Project Advice
EBOM-2009 EAc1:Optimize Energy Performanceposted by Johanna Hendricks on
Hello, We have a client that has approached us about the possibility of certifying a golf course clubhouse via LEED EBOM.
Building Occupancy for Performance Period
EBOM-2009 EAc1:Optimize Energy Performanceposted by Galen Staengl on
Is there a minimum building occupancy % for the 12 month performance period? I am working on an office tower that has slowly increased it occupancy over the last year.
International Project - Case 2 Option 1 or Option 2
EBOM-2009 EAc1:Optimize Energy Performanceposted by Sheena Moses on
Dear all, The case 2 calculator has pointed us towards using Case 2 - Option 1 for our Existing Retail Mall project located outside of the US.
Sharing the Portfolio Manager facility profile
EBOM-2009 EAc1:Optimize Energy Performanceposted by Carrie Bradley on
LEED EBOM v2009 allows you to skip the SEP submittal if you share your Portfolio Manager facility directly with the USGBC review team.
EAp2 Case 2B Fulfillment
EBOM-2009 EAc1:Optimize Energy Performanceposted by Jessica Bruscato on
Being that my project is a convention center, it does not qualify for energy star.
On Site Solar Power
EBOM-2009 EAc1:Optimize Energy Performanceposted by Julia Weatherby on
Energy Star Portfolio Manager requires that power produced and used on site be included when submitting for an Energy Star rating.
Church+Classrooms = Office?
EBOM-2009 EAc1:Optimize Energy Performanceposted by Charles Shinneman on
I have a church that runs extended house 9am-10pm 6.5 days a week has classrooms that are not heavily occupied. In classifying it the occupancy looks more like an office with extended hours.