Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Wed Aug 1, 2018, 10:14 pm

Energy Star approach for a campus with shared parking

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  F. Borja López Calle  on 

Good morning.I am working on a LEED project that was registered under LEED EB: O&M 2009 that classifies as LEED campus as well.

2
Senior Sustainability Manager
WSP - Built Ecology
LEEDuser Expert
188 thumbs up
Sun Sep 24, 2017, 5:42 pm

International Project not eligible for Energy Star Rating

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Se Hyeung Pak  on 

Hi, I am involved in EBOM case located in Korea. I have a couple of Qustions based on the case. We needs to meet the requirements of LEED O&M Certification EA Pre-requisite Case2 option1.

1
Wed Oct 29, 2014, 3:41 pm

Portfolio Energy Star

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Mercè Llorca  on 

Hello. We will make the Eap2 by Energy Star. To do this we have invoices for the total consumption of the building (offices + CPD), and manual readings consumption of different meters.

1
Wed Feb 3, 2016, 4:20 pm
1
Fri Sep 3, 2010, 11:35 am

Central Chiller Plant - Chilled Water Btu Metering

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Simon Sue  on 

A central chiller plant supplies chilled water to our project building and several other buildings.

1
Thu Jun 23, 2011, 11:29 pm

Partial Building Energy Star Score

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  SIG - Sustainability Main Account  on 

I am analyzing a 40 story vertical mixed use tower for LEED EBOM. It is split 50/50 between office and condos-both under separate ownership, management, and metering.

1
Wed Feb 22, 2012, 12:26 am

EAp2/EAc1 - Case 2 Option 2b

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Peter Locke  on 

We are submitting a museum bldg and have had confirmation from GBCI that we can use Case 2 - historical data to compare against.

0

water bills received every 3 months

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Agnieszka Rylska  on 

Our project receives water bills including water usage every 3 months.

1
Wed May 18, 2016, 5:12 pm