FAQs about EAp2 :

We have installed submeters on our building but the utility bill includes energy use from several other buildings located on the same campus. How do we reconcile this during the LEED review process?

When is it possible to exclude up to 10% of the building from EAp2?

What do I do if the number of building occupants, operating hours, or vacant space changes during the performance period?

If you pursue the streamlined path for an Energy Star label, should the performance period for EAc6 match the 12-month time frame of the label?

How do I account for computers with multiple monitors on Portfolio Manager?

How should I treat vacant space on Portfolio Manager?

Our building includes a large laboratory space. Can our project benchmark under the Labs21 program?

We have an international project and the space type is eligible for an Energy Star rating. Can we pursue Case 1 to demonstrate compliance given the recently released alternative compliance paths for international projects?

We have a number of buildings on a single campus that we would like to certify at the same time. Is it possible to benchmark the buildings at the campus level?

I have a mixed-use building and am wondering if it is possible to pursue the prerequisite through Case 1. How do we proceed?

We have a building that consists of two attached structures and it’s unclear if we have to consider it a single building or if it should be certified as two separate buildings and benchmarked accordingly. How should we proceed?

How long is an Energy Star label valid to use with a streamlined approach for Case 1?

Our building includes heavy process loads that significantly increase the overall energy use in the building. If we submeter these loads, can we exclude this energy use for benchmarking purposes?

View answers »

Forum discussion

EBOM-2009 EAp2:Minimum Energy Efficiency Performance

Stremlined Path vs. No Energy Star Label?

If the building was awarded an Energy Star label in April 2013 with 80 points and now we are submitting for certification in January 2014 (less than a year from being awarded the label). If we found out that at the end of the PP the current score has been improved and it is now 82 points Can we select the "No Recent Label" and use the new figure and gain the 2 extra points OR it will be flagged as "You DO have a recent Label within the last 12 month from the submittal date and the project should seek the Streamlined Path?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 03/11/2014 - 01:13

Hello Jalal: It's your choice. In LEED Online, the streamlined paths are always optional, never required. The intent is to give you flexibility in how you document EAp2, not to force you down a certain path. So, if you prefer to use the standard documentation path in LEED Online to take full advantage of your improved score of 82, that's perfectly fine. No one at GBCI will object; in fact, they will celebrate that you have improved your building! Mike

Add new comment