Construction IAQ Management Plan—Before Occupancy
Filter by location
Forum
Topic
Replies
Recent

Timing of IAQ testing compliance

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Anders Olson  on 

I am part of a LEED NC 2009 for Retail project that intends to pursue Option 2 -- Air Quality Testing -- for this credit.

4
Sustainability Manager
Clark Builders
LEEDuser Premium Member
8 thumbs up
Tue May 8, 2012, 8:17 pm

Flushout calcs for Option 1 Path 1

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Mark Haynie  on 

To achieve the required time needed for flush out, do we only take into consideration the OA louver volume (CFM)?

2
Default Avatar
CIH, LEED AP, CBCP
CIH Environmental Solutions
LEEDuser Basic Member
3 thumbs up
Tue May 8, 2012, 3:47 pm

Option 1 Path 2

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  shaun Andriano  on 

Hello. We have a building looking to meet the requirements for Option 1 Path 2. In the credit language it states that the flush is to stop at the end of occupancy for that day.

9
Tue Apr 17, 2012, 4:41 pm

Warehouse Flush Out

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Curt Pascoe  on 

Both NCv2.2 and v2009 are clear with the temperate and humidity constraints.

2
P.E., LEED AP BD+C
Ryan Companies US, Inc.
LEEDuser Basic Member
87 thumbs up
Tue Sep 6, 2011, 12:27 pm

# Of Testing Locations

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Dan Forino  on 

Our project single floor mixed use space, with a large single heat recovery unit providing outside air to all of the spaces.

2
Sustainability Director
RDG Planning & Design
LEEDuser Basic Member
8 thumbs up
Mon Aug 22, 2011, 7:33 pm