IAQ Testing - Maximum Concentrations
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Donald Green on
Can anyone tell me where the Maximum Concentrations listed in the reference guide came from? Who established them, is there a document or website that can be visited? Thank you,
IEQc3.2 Option 2: Air Testing
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Christopher Strunk on
Currently doing a LEED v.2009 project and are looking to pursue IEQc3.2, Option 2. We got a question from the air quality tester asking about the specific requirements for testing.
Do all units have to run at 100% OA for this credit?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Saju Varghese on
We have 4 A/C Units providing air conditioning to a building, two of them are 100% OA units and two of them are providing the total air supply cfm (OA + recirulated air) is 7000 cfm and 8600 respec
furnitures installed before the flush out
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Benjie Herrera on
Can furnitures be installed before the flush out?
Option 2 fails TVOC - will Retest Pass?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Sandi Carney on
I was the responsible party who ran the baseline IAQ testing event a a newly constructed 6,000 SF teaching facility. The TVOC results came back yesterday and were 4,900 ug/m3.
Air Sampling
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Farah A. on
If a building is 25,000 sq feet, does that mean only one air sample needs to be taken? Or is it more dependant upon the number of HVAC systems/building area?
Definition contiguous floor area
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Lise Dannesboe on
Hi! I was wondering how to interpret the term "contiguous floor area" in IEQ CREDIT 3.2 Option 2 Air Testing.
Flush out and data center
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Lise Dannesboe on
We are pursuing option 1 Flush Out. Our building includes a large datacenter.
Flush out in a Warehouse
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Paula Hernandez on
Hello to everyboty and Merry Christmas, I have to make the flush out in a building which is mostly a Warehouse, that will be regularly occupied, with mechanical ventilation but no air conditioning.
air testing in a mechanical room??
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Carrie Laurendine on
1) Do mechanical rooms need air quality testing? 2) There is an air handler unit that supplies air to multiple floors.