New IEQc3.1 Filtration Media Requirements?
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by R. Ted Krasnesky on
I recently opened the LOL V3 NC form for IEQc3.1 and found that Table IEQc3.1-1 has three new columns - CEN Rating, Min Dust Spot Eff and Arrestance in additon to the MERV rating.
EQc3.1 IAQ Construction during construction
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Kimo Steed on
We are building a new building with concrete precast wall and roof panels with a concrete slab-on-grade.
Pesticides during construction
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Omar Elrawy on
Dear all, During the construction phase, the contractor asked to use pesticides once per week within the building.
One or Two Documents
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Omar Elrawy on
I'am confused about the document entitled "IAQ Management Plan" that is required under both; IEQc3.1 and IEQc3.2. Should I prepare only one document including IAQ during construction and flush-out
Unrated filters
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by kathy zarsky on
We are using Mitsubishi fan coil units on a project and provided a description of the permanent filter type in lieu of the MERV rating requested in the table for IEQc3.1.
Doing monthly photo report of IAQ management
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Indochine Engineering VN on
Hi, My project is under construction, but just structural work (finalizing substructure and launching superstructure). It is long way to furnishing and MEP work onsite.
Checking oh IAQ management plan during construction
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Caroline PIN on
Dear all, I read it's necessary to do 3 date & time stamped visits with 6 photo for each visit to submet on LEED Online IEQ credit 3.1. It is true ?
HVAC system wasn't running during construction
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Juanita Garcia on
If the HVAC system wasn't running during construction of a new building, what is the requirement for documentation? We have dated checklists documenting that the HVAC system wasn't running and that
Is the credit for during construction, or after envelope is up?
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Nelina Loiselle on
We have an issue with a General Contractor on a project.
Plenum Return Systems
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Nate Maniktala on
Hi All, Compliance with this credit in fully ducted return systems has been straight forward, however, the LEED Reference Guide is not too clear on how exactly open plenum return systems are to be