NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Seung Jae Lee on
I have a question relating to NC IEQ C 1.
Locker rooms
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Agnieszka Rylska on
Are CO2 sensors required in locker rooms? Loker rooms are non-regularly occupied spaces but they are also densely-occupied spaces.
Special Circumstance - Ventilation Air Not Required
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Charles Daze on
We have a building with a large area of lockers/toilets. According to ASHRAE 62.1 these spaces do not require ventilation air. These spaces do require exhaust air.
Alarms with CO2 sensors
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Instra Ingenieros on
hi, We have a project with non-densely spaces. The non-densely space will have CO2 sensor. VAV with 100% outdoor air will be supply the OA to these spaces.
C02 Monitoring Project
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Aaron Doherty on
Hi all, I am doing an undergraduate senior project for my major requirement in my University. My partner and I are planning to monitor the levels of C02 in dorm rooms on campus.
n/a
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Stella Stella on
Hi, We have a project with some areas served by AHUs and some areas served by contant volume FCUs.
Laboratory Classrooms
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Crina Bosch on
We have a lab classroom building that is served by an 100% OA unit. It maintains 6 ACH in all the lab spaces for ventilation while in use.
Outdoor air monitoring in corridors with induced ventilation
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Ricardo Sá on
We are currently working in a project where outdoor air requirements in corridors are met by means of induced ventilation (exhaust fans in contiguous WC's induce make-up air in the corridors).
Table IEQc1-2 Outdoor Air Ventilation Rate
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Thomas Hellmann on
According to IEQc1, I am to complete table IEQc1-2 for all systems where 20% or more of the design supply airflow serves non-densely-occupied spaces.
addition project compliance)
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Saju Varghese on
when I have an addition project do I have to demonstrate compliance for the new addition and renovated areas or does it have to be applied to all areas? (existing to remain, renovated and new)