Forum quick links
District Cooling System
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Roland Le Roux on
Hello, I have two questions regarding a district cooling system to be used in one of our projects: 1- Can we use 0.51% value for Refrigerant leakage rate and 2% for end of life refrigerant if the
Refrigerant Calculator and Thermal Storage
NC-2009 EAc4:Enhanced Refrigerant Managementposted by James Keohane on
Which tonnage should be used when using refrigerant calculator while considering a chiller plant serving a static ice thermal storage system?
Enhanced Refrigerant Management - Purchased Cooling Loop
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Vinny Greco on
If a university building is tied in to a campus chilled water distribution, does the campus chiller plant have to be included in the building's refrigerant use?
Tonnage Associated with Energy Recovery Equipment
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Rebekah Burke on
Is the tonnage requirement for the credit supposed to include compressor capacity only or can additional capacity from energy recovery devices be included in the tonnage?
Old refrigeration equipments in new construction.
NC-2009 EAc4:Enhanced Refrigerant Managementposted by James Chueh on
Hi all, The project we are working on will have old refrigeration equipments moved from other place.
Long Term Service Contract
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Erin Holdenried on
Does anybody have an example of a long term service contract, or know specifically what needs to be included in the contract in order for it to be accepted by the GBCI reviewer?
Notes under table in LEED credit form
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Patryk Marciniszyn on
Hi all, under the table in LEED credit form there is a note: Average refrigerant impact per kW must be less than or equal to 13 for 2 points. Does it mean that I won't get 2 points for having av
Acronym ARI
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Cédric Marzolf on
Little question : What does the acronym of ARI mean in the credit guidance?
Water heat pump
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Instra Ingenieros on
Hi, We received the design and construction review, and the reviewer indicate us that two units that's appear on the prerrequisite EAp3 documentation are not included.
GE Profile 21.7 &15.5 Cu. Ft. Top-Freezer Refrigerators
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Waylon Lo on
We've tried and cannot get any info from GE other than they use R-134A refrigerant.