Systems Manual - third party PV system

NC-2009 EAc3:Enhanced Commissioning
posted by  Lisa Logan  on 

Reviewer said that we need to include the PV for our project in the systems manual. The PV was exisitng (previously commissioned) and is owned, operated and maintained by a third party.

3
Default Avatar
Senior Sustainability Consultant
Noresco
LEEDuser Premium Member
0 thumbs up
Mon Nov 18, 2013, 5:53 pm

System's Manual in American English

NC-2009 EAc3:Enhanced Commissioning
posted by  Alicia Villanueva  on 

After submitting the documentation for this credit, we have been requested to translate the System's Manual to America English. The System's Manual we uploaded is composed of 494 pages, 486 of whi

3
Mon Oct 28, 2013, 1:20 pm

Health Care vs Canada New Construction 2009

NC-2009 EAc3:Enhanced Commissioning
posted by  Shevaun Barrie  on 

Hi, Does anyone know if there are any extra requirements aside from the optional BECx in LEED for HC vs Canada NC 2009? I can't see any but have been told there are more visits required.

5
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Thu Sep 5, 2013, 8:24 pm

Sub-consultant to CxA

NC-2009 EAc3:Enhanced Commissioning
posted by  Lise Dannesboe  on 

Hi. We have a project over 50.000 sf, where an individual from the Owner is CxA. He would, however, like to hire a sub-consultant to handle some of the work during the construction phase.

5
Sustainability Manager
COWI
LEEDuser Premium Member
54 thumbs up
Wed Aug 21, 2013, 9:48 am

CxA contracting for enhanced commissioning in a design&build pro

NC-2009 EAc3:Enhanced Commissioning
posted by  Valentin Grimaud  on 

Dear All, We have a 300,000sqft project, quite technical facility. It is a design&build contract and the owner is reluctant on taking independent contracts on his own.

11
Default Avatar
Senior Architect
Benham, A Haskell Company
LEEDuser Premium Member
0 thumbs up
Thu Jul 18, 2013, 4:38 pm

Stair Pressurization Fans and Booster pumps

NC-2009 EAc3:Enhanced Commissioning
posted by  Bob Crowell  on 

Are the following systems required to be tested under the LEED Commissioning Scope? 1. Stair Pressurization Fans 2. Domestic Water Booster Pumps 3. Grey water reuse system Thank you,

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri Jul 12, 2013, 2:56 pm

Same firm as sub-contractor and CxA

NC-2009 EAc3:Enhanced Commissioning
posted by  Sally Marr  on 

I am working on a Design-Build project of over 50,000 sf for which the contractor has hired a certain firm to do the testing and balancing.

2
Default Avatar
Commissioning Engineer
LEEDuser Basic Member
15 thumbs up
Wed May 22, 2013, 9:46 pm

Building Envelope Commissioning LEED required test methodology

NC-2009 EAc3:Enhanced Commissioning
posted by  Pablo Fortunato Suarez  on 

Our project has included Building Envelope Commissioning as part of the scope of Enhanced Commissioning plan.

2
Fri May 17, 2013, 8:10 pm

(Jacob) Labs and Other Energy Intense Areas to be Included?

NC-2009 EAc3:Enhanced Commissioning
posted by  Brett Beckemeyer  on 

My current project contains a non-manufacturing lab and research facility. The entire lab and research facilities probably incorporate a large portion of the buildings overall power consumption.

2
Fri May 3, 2013, 1:27 pm

choosing the CxA for Enhanced Commissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  Marina Andrade  on 

A project we are working on already has a CxA for the Fundamental Comissioning (Independent consultant contracted by the Owner). Can the CxA for the EAc3 be different from the EAp1 CxA?

5
Fri Nov 30, 2012, 9:53 pm