CHP Modeling
NC-2009 EAc1:Optimize energy performanceposted by SAMY Chamy on
Dear Marcus..... Greetings... In one of our project , we have CHP which fall under Case 1 as given in LEED Guide, CHP under Same Ownership..We have 2 nos of 500 KW Gas Generator which supplies
ASHRAE compliance with naturally ventilated building
NC-2009 EAc1:Optimize energy performanceposted by Jean Marais on
As per the guidelines, my baseline mechanical system is incorporated into the naturally ventilated design case model 1 to 1, as a priority 2 kind of system that kicks in when the naturally ventilat
G.3.1.3.14
NC-2009 EAc1:Optimize energy performanceposted by Francesco Passerini on
As baseline model I have to model a System 6.
Prescriptive EnergyEfficiency nApproach
NC-2009 EAc1:Optimize energy performanceposted by J.R. Anderson on
The LEED 2009 v does not specify the level of efficiency for a small office / mixed use building. Only AEDG 2004 is shown specified.
Greenhouse energy consumption
NC-2009 EAc1:Optimize energy performanceposted by Karl Heitman on
We are working on a factory in Chicago which will have food producing greenhouses on the roof.
LEED --NC 2009 Summitals platmatel EA credit 1
NC-2009 EAc1:Optimize energy performanceposted by Yu Tang c850802@ms10.hinet.net on
Hello,Anyone : Who can help me where can find LEED --NC 2009 Summitals platmatel EA credit 1 Thanks and best regards, Y.T.
Appendix G - Baseline Building Rotations
NC-2009 EAc1:Optimize energy performanceposted by Kalyan Nishtala on
Hi All, Are baseline building rotations necessary for a new building that is connected to an existing building. Note that the new building is being modeled as a stand alone.
Process Load
NC-2009 EAc1:Optimize energy performanceposted by Muzammal Abbas on
Dear all, We are doing a factory project in pakistan, which have a 1200 kw process machinery load, after energy modeling without process load we are saving 55 % from baseline but after adding proce