ARI Certification for VRF equipment in LEED-NC 2009

NC-2009 EAp2:Minimum Energy Performance
posted by  Mauricio Ramirez  on 

Talking about a VRF HVAC system. Is it a mandatory requirement that the VRF condenser and evaporative units must be ARI Certified, according with the Standard 90.1-2007?

1
Tue Feb 14, 2012, 3:26 pm

IES ApacheHVAC - Proposed system for VRF

NC-2009 EAp2:Minimum Energy Performance
posted by  Alice chen  on 

Hi All, I am modelling a VRF system using ApacheHVAC in IES. But have no idea which prototype to choose.

0

Lighting power density of a Clinic

NC-2009 EAp2:Minimum Energy Performance
posted by  Rodrigo Dias  on 

Hello I'm working in a energy simulation of a medical clinic, where it is possible to make some types of exams and diagnoses, but it doesn't have spaces like intensive care or surgical areas.

1
Sat Nov 24, 2012, 8:34 pm

Treatment of Outdoor Air for Incomplete Spaces

NC-2009 EAp2:Minimum Energy Performance
posted by  Joseph Chappell  on 

I recently received LEED review comments regarding the treatment of incomplete space in an energy model for a proposed new construction building.

1
Tue May 30, 2017, 8:24 pm

Automatic shades with manual control

NC-2009 EAp2:Minimum Energy Performance
posted by  Erika Duran  on 

ASHRAE 90.1-2007 mentions that for the Proposed case automatically controlled fenestration devices or shades may be modeled, but manually controlled shades should not be modeled.

1
Mon Jul 22, 2013, 2:16 pm

Exceptional Calculation for Elevator

NC-2009 EAp2:Minimum Energy Performance
posted by  Thomas Hellmann  on 

My read on ASHRAE-90.1 and numerous forums, is that USGBC may allow for an exceptional calculation to be performed for elevator energy savings, provided that; 1) Schedule of operation remains the s

1
Wed Mar 14, 2012, 3:56 pm

Suspended Ceiling

NC-2009 EAp2:Minimum Energy Performance
posted by  Omar Elrawy  on 

Dear all, I have a suspended ceiling with a 60 cm air gap between the panels and the reinforced concrete slab where all the electro-mechanical lies, but it doesn't act as plenum zone si

1
Mon Apr 14, 2014, 6:17 pm
1
Thu Sep 30, 2010, 2:24 pm

Core Performance Guide

NC-2009 EAp2:Minimum Energy Performance
posted by  Tricia Loe  on 

I have a project that is considering using the Core Performance Guide option for compliance with this credit.

1
Wed Aug 16, 2017, 7:11 pm

Plant Design for Proposed bldg

NC-2009 EAp2:Minimum Energy Performance
posted by  Julian Park  on 

If a new building will be served by an existing chiller plant that already serves an existing building, does the Plant design for the Proposed Alternative need to model the full chiller size, even

1
Thu Mar 5, 2015, 5:35 pm