Energy Update ballot

NC-2009 EAp2:Minimum Energy Performance
posted by  Kathryn West  on 

when will the results of the ballot be posted?

0

Unitary Cooling Efficiencies

NC-2009 EAp2:Minimum Energy Performance
posted by  TOMAS URIBE  on 

Hello, We are simulating a type 4 system in our baseline and need to know if the efficiency ratings specified in table 6.8.1B (and tables 6.8.1.A, 6.8.1D) do include supply fan power and hence ne

1
Tue Jul 10, 2012, 1:34 pm

Change form

NC-2009 EAp2:Minimum Energy Performance
posted by  Nicolas Martinez Ochoa  on 

Hi, I am working in an office building. I have completed the “minimum energy performance v2009” spreadsheet, but the project uses the v05 form. Is it possible to change the form to a newer form?

1
Tue Nov 8, 2016, 10:53 pm

Zone isolation

NC-2009 EAp2:Minimum Energy Performance
posted by  Ricardo Sá  on 

In an office building, shall meeting rooms (sporadically occupied within the schedule defined for the remaining occupied office areas) be considered an isolation zone according to ASHRAE 90.1 (2007

1
Tue Oct 22, 2013, 8:09 pm

Energy Model Baseline for a Dome

NC-2009 EAp2:Minimum Energy Performance
posted by  Nelina Loiselle  on 

We have a data center project where the owner decided to design-build a dome structure because of the efficiencies inherent in this type of construction.

1
Mon Sep 19, 2011, 5:20 pm

Denial of EA PR2

NC-2009 EAp2:Minimum Energy Performance
posted by  Roxanne Button  on 

A client has asked for my advice in appealing the denial of PR2. I've taken a quick look at the review comments but will be digging deeper into it in the next couple of days.

1
Fri Mar 25, 2016, 2:35 pm

Basecase Building Envelope

NC-2009 EAp2:Minimum Energy Performance
posted by  SAMY Chamy  on 

Dear All:- we have two major renovated Building in India Building 01. No change in building envelope (used the existing wall, floor, window) but changes in whole MEP Design Building 02.

1
Thu Dec 22, 2016, 3:47 pm

Major Renovation Requirements

NC-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

When a project would be classified under Major Renovation (our project is around 80% renovated) for the energy model, does the baseline have to be the same as Ashrae 90.1 envelope requirements or c

1
Wed Apr 24, 2013, 9:10 pm

LEED Project boundary and EAp2, EAc1

NC-2009 EAp2:Minimum Energy Performance
posted by  Kim Sosalla-Bahr  on 

The project is a new facility, which has a new construction and renovation component. The new building is 6 stories tall, adjacent to an existing 3 story plus roof deck building.

1
Mon Oct 10, 2011, 3:50 pm

LEED NC V2009 - Data Center

NC-2009 EAp2:Minimum Energy Performance
posted by  SW LEE  on 

Our project owner would like to register a Data Center under LEED NC V2009. May I know, do anyone know how to simulate the data center?

1
Mon Apr 25, 2016, 3:46 pm