Post a question or comment
Credit Filters
Heat Island Effect—Roof
Filter by location
Forum
Topic
Replies
Recent

ROOF CORRIDORS WITH MULCHING

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  RICARDO HERNANDEZ  on 

I'm pursuing the credit with the 50% of vegetated roof but the landscape architect considered almos 1500 sq ft. of gravel and rocks for corridors, without this 1500 sq. ft.

1
Thu Mar 21, 2013, 2:43 pm

100% Glass roof

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Trinidad Guajardo  on 

Our project is a showroom for trucks that considers a 2 story building as sales room and an outside exhibition of the trucks.

1
Fri Dec 20, 2013, 9:01 pm

Green Roof Plant overhang

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  John Covello  on 

Hello, We have larger planters set upon our project's roofs. The rest of the roof area will be covered in gravel. Much of the plant growth will droop and overhang onto the gravel.

0

White Membrane Roofs and Dirt

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Carrie Webster  on 

We are often disappointed by how muddy and stained our high SRI low-slope membrane roofs are when the building is turned over from the contractor.

1
Wed Jul 6, 2016, 3:00 pm
1
Thu Apr 22, 2010, 12:35 am

Manufacturer information on SRI not available

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Magda Aghababyan  on 

I was looking for manufacturer data sheets to confirm the SRI for Zn-Al coated roofing (Silver color) but in Sri Lanka the suppliers do not have that information available. Can you please tell me

1
Tue Jul 30, 2013, 4:53 pm

Roof area exempt from the SSc7.2 calculation

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  FABIO VIERO  on 

We have a project with a terrace that is about 50% of the building roof.

1
Fri Nov 27, 2015, 3:07 am

PV Panels on roof

posted by  Deborah Lucking  on 
1
Wed Aug 4, 2010, 8:46 pm

Metal grating roof

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  MARIA GARCIA  on 

Hi all, We have a roof above an unconditioned floor with the mechanical equipment and we dont know what to do about the SS c 7.2.

1
Wed Nov 9, 2011, 11:20 pm

Major refurbishment - existing building

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Alicia Freire  on 

Can this credit not be achieved in an existing building where one floor (not the top floor) is being assessed and the existing roof will be left untouched?

1
Fri Nov 1, 2013, 1:51 pm