BMP Non Compliance and / or Removal of BMP Mid-project.

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Richard Palmer  on 

Please could someone advise as the best way to report the removal of a BMP from the ESCP midway through the project?

1
Mon Mar 3, 2014, 8:15 pm

"Rain event" definition

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Noriko Nagazumi  on 

Hello. Would someone please define "rain event"? Is it the total rain since the beginning to the stop of a rain?

1
Fri Sep 11, 2015, 6:25 pm

Air Pollution

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Lu Anne Nielsen  on 

SSp1 was marked under pending for my current project.

1
Sun Apr 24, 2011, 3:30 am

What are the requirements for the inspectors?

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Jose Gonzalez  on 

We are completing a high-rise in Surfside, FL and we fall under the jurisdiction of FDOT, FDEP, and the EPA as this is a Beach side construction.

1
Wed May 23, 2012, 7:58 pm

Documentation for small sites without SWPPP

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Norma Lehman  on 

For the first year of construction, our project site area was smaller than the area that requires SWPPP inspections/reports.

1
Sat Aug 26, 2017, 1:59 pm
1
Fri Apr 2, 2010, 1:16 pm

Dust Reduction (general and from a concrete crusher)

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Sam Keehn  on 

Our project is located in an extremely dusty location outside of the U.S. with very light annual rainfall. The project footprint is about 30% of the overall site.

1
Wed Nov 2, 2011, 11:32 pm

ESC plan implemented after or at the commencement of excavation?

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Valentin Grimaud  on 

Hi All, we are wondering if the general contractor should implement the ESC at the same time of the leveling and excavation works begin, or if it could done after?

1
Fri Nov 23, 2012, 3:54 am

Sandy soil

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Rustem Saitov  on 

Could anyone kindly clarify the following issue: I work with a project on construction of industrial plant.

1
Fri Jul 25, 2014, 4:54 pm

ESC Plan and Project LEED Boundary in Campus project

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  soha yamani  on 

we are working on a campus LEED project that have four different contractors working on four different buildings that will be registered for LEED as individual projects under campus project now so

0