Conditions for site fence
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Julian Bork on
Hello everybody I have a question about the construction fence as a part of the ESC plan: is there a minimum height for closing or covering the fence with tarpaulins to avoid wind erosion? Many th
Is demolition also part of the ESC-plan
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Christian Brücher on
Hello, I have got a question concerning a project which will start within the next weeks. Before the start of earth and construction works, an old building on the site has to be demolished.
Maintenance Plan for ESC
NC-2009 SSp1:Construction Activity Pollution Preventionposted by JP Rout on
Is maintenance plan a mandatory requirement under ESC and what should be its content? Kindly share if any sample is available. Thanks in advance.
Previously developed or graded land
NC-2009 SSp1:Construction Activity Pollution Preventionposted by SoYoung Lee on
We are planning to pursue LEED certification for the official buildings.
International Project Epa CGP
NC-2009 SSp1:Construction Activity Pollution Preventionposted by ESRA OZKONUKSEVER on
Hi Y'all, we re working on a project in Turkey and creating an ESC and a SWPPP plan.
ESC plan language
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Aldo Pazo on
Hello everybody. Can we submitt in LEED Online our ESC Plan in other language different than English? for example in Spanish? Thank you!
Preliminary earthworks before project registration
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Amanda Johnson on
Hello, For complicated planning reasons on a large (probably Campus) project some preliminary earthmovement and demolition will take place soon, but the project is not yet registered.
Credit Interpretation Request to support SS p1.
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Marie-France Duthilleul on
When comparing your proposed ESC PLan Is there standard text language / narrative that clearly describs the requirements of Phase 1 and Phase II of the NPDES program.
Inspection Reports - responsible party
NC-2009 SSp1:Construction Activity Pollution Preventionposted by komal kotwal on
Is it required that the on-site inspection be conducted by a third party or can a Contractor's representative conduct the same?