Hello,
For complicated planning reasons on a large (probably Campus) project some preliminary earthmovement and demolition will take place soon, but the project is not yet registered. An ESC plan will be included with the bid-set and will be implemented during the work, as well as any waste tracking.
Is this going to be a problem?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $15.95 »
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
June 30, 2014 - 12:20 pm
Amanda, this is not a problem with regards to LEED. There is no requirement to have a LEED registration in place before project work begins. I would just recommend being aware of key prerequisites and documentation needs, as you seem to be.