Hello,
I have got a question concerning a project which will start within the next weeks.
Before the start of earth and construction works, an old building on the site has to be demolished. Do we already have to develop and install an ESC-plan for the demolition works or is it compliant to start afterwards when the excavation and earth works for the basement of the new building will begin?
Thanks for helping!
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
April 19, 2011 - 3:41 pm
Christian, the ESC plan should be in place for the whole project. If demolition is in the scope of the project, then the ESC plan should be applicable to that.