Vertically attached - clarifications

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Martin Meehan  on 

Quoting MPR Supplemental Guidance document (Buildings attached to non-certified buildings, page 17): "1) VERTICALLY ATTACHED, LEED-EB: O&M, AND MAJOR RENOVATION PROJECTS If the certifying proj

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Fri Jan 20, 2017, 8:01 pm

Horizzontally attached bldg addition to Non Certified building

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Tesfa Bogale  on 

We are working on a new building addition. The new addition building will be attached horizontally to a non LEED-Certified building.

7
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Thu Sep 15, 2016, 1:48 am

2 buildings but cannot function independently without the other

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Miriam Ramirez Baumgarten  on 

Hi, We have a project that includes a Hangar, with two levels of administrative offices and workshop area in one 250,000sf building.

4
Default Avatar
LEEDuser Premium Member
19 thumbs up
Mon Aug 8, 2016, 6:28 pm

Single Building Certification_LEED New Construction 2009

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Aswin M  on 

We have a Garment factory project that has three blocks with connectivity bridge.  The three blocks are namely Cutting block, Sewing block, and Fabric store block.

7
Default Avatar
Conserve Consultants Private Limited
LEEDuser Basic Member
5 thumbs up
Wed Dec 30, 2015, 5:06 am

Resort Hotel and Condo

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  John Zehren  on 

I am working on a 7 story resort hotel and condo under LEED 2009 NC. We just received word that the 9 Condos on floors 6 and 7 will be finished at a future date.

4
Default Avatar
Zehren and Associates
LEEDuser Basic Member
2 thumbs up
Fri Dec 18, 2015, 12:01 am

Office tower on a shopping center "plinth"

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Ricardo Sá  on 

I'm working on a project that consists of an office building tower that will be erected on top of a shopping center built 20 years ago.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Nov 30, 2015, 4:28 pm

Tenant Guidelines for CS spaces within NC

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Melanie Silver  on 

We are working on a large residential project that has two very tiny retail spaces at the base (one less than 500 sf, and the other about 1500 sf).

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Nov 30, 2015, 3:13 pm

Major renovations

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Veronica Reed  on 

Hello, what level of intervention would constitute as "Major Renovation"?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Sep 30, 2015, 6:04 pm

Residential high rise with school at the base

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Ilana Judah  on 

We are designing a high-rise residential tower with a school and retail area at the base. There is some entry and service space serving the residential tower on the cellar and ground floor levels.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Aug 5, 2015, 2:32 pm

Existing Building Renovation and Site Work

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Catherine Adams  on 

We have an existing two-story community recreation center with an adjacent parking lot. Most(about 75%) of the building interior will be renovated, with some new windows added to the perimeter.

3
Architectural Associate
Astorino|CannonDesign
LEEDuser Basic Member
0 thumbs up
Tue Jun 9, 2015, 9:15 pm