Non-certified buildings in LEED boundary
NC-v4 MPR2:Must use reasonable LEED boundariesposted by marty seese on
I have a project that is all new construction. There are 3 buildings on the site. The main building which is what the owner wants to be LEED Certified. Another building is a shed building.
Interpretation of text relating to Envelope
NC-v4 EAp1:Fundamental commissioning and verificationposted by Keith Fahy on
Hi, see here an extract from the Reference Guide: "The envelope must be covered in the OPR and BOD, but full envelope commissioning is not required unless the project team pur
Disinfectants with EPA Registration No. and on List N: Disinfectants for Coronavirus (COVID-19)
EBOM-v4 EQc7:Green cleaning - products and materialsposted by DINGTIAN OU on
Few green disinfectants (e.g. Green Seel, UL or EPA Safer Choice Standard certified) are available in Hong Kong market.
Our clients proposed two commonly used disinfectants:
District cooling chilled water
CS-v4 WEc2:Indoor water use reductionposted by Dina El-Sady on
If the project is served by a district cooling plant outside LEED project boundary , does the chilled water count as process water and needs to be included in water efficiency calculations?
All-Gender Restrooms - Verticality (Locate on all levels or selected levels?)
NC-v4 INc1:Innovationposted by Vijitha Mammen on
We are working on a post-secondary education project incorporating both gendered and all-gender restrooms.
WEp2c2 Indoor Water - calculating urinal access for multiple single user WCs
NC-v4 WEp2:Indoor water use reductionposted by Susan Di Giulio on
Our project is a machine/model-making shop in an art and design college. There are 4, ungendered, single-user bathrooms that all occupants have access to (no other bathrooms).
LOCALIZATION OF STORAGE AND COLLECTION OF RECYCLABLES
Hospitality-NC-v4 MRp1:Storage and collection of recyclablesposted by Andrea gamio on
Well, my answers is about the better location of the dumpsters. Our project is a boutique hotel in the historic neigtboardhood town of spain, and the building is smaller.
Heat Pump Room = Mechanical Room?
NC-v4 EQc9:Acoustic performanceposted by Iris Meeker on
We are trying to determine whether or not a Heat Pump Room would be considered a "Mechanical Room" for purposes of the Acoustic Performance credit?
Does the project scope for kitchen appliances include future tenants?
NC-v4 WEp2:Indoor water use reductionposted by Christoph Keck on
Hi guys,
LT credits for regional priority
NC-v4 LTc1:LEED for Neighborhood Development locationposted by Emily Purcell on
Hi,