CFR and O&M Plan vs Systems Manual and OMM
CI-v4 EAp1:Fundamental commissioning and verificationposted by Tom Poyner on
Looking at the requirements for the CFR and O&M Plan, it appears to have some cross-over with the Systems Manual and O&M Manual. Is it the intention that information is duplicated? How do t
Engaging the CxA
CI-v4 EAp1:Fundamental commissioning and verificationposted by Jeni Panars on
This pre-requisite requires the CxA be engaged by the design development phase. The client for the project I am working on did not decided to pursue certification until 100% design.
v3 vs. v4 Fundamental Commissioning Scope
CI-v4 EAp1:Fundamental commissioning and verificationposted by Jareb Ketay on
Hi everyone!
Envelop Commissioning
CI-v4 EAp1:Fundamental commissioning and verificationposted by Peter Doo on
The LEED Online template provides selections for HVAC systems commissioning (4pts) or commissioning with monitoring (5pts). The LEED Reference Guide describes Enhanced Systems Commissioning (3-4pts
BOD and OPR
CI-v4 EAp1:Fundamental commissioning and verificationposted by Erin Rowe on
I am looking at an OPR for a project pursuing this credit, and it is quite high level.