No cooling tower - District cooling
NC-v4 WEc3:Cooling tower water useposted by Martina Salonen on
Hello! We have project which would be applicable for the 'no cooling tower' alternative compliance credit. However, the client is now considering connection to the district cooling system.
Which parameters of the cooling tower?
NC-v4 WEc3:Cooling tower water useposted by Jade Deltour on
Which parameters/performances of the cooling tower need to be checked/optimised to limit tower cycles to avoid exceeding maximum values?
No Cooling Tower - Alternative Compliance Path
NC-v4 WEc3:Cooling tower water useposted by Kristina Pobre on
My project does not have a cooling tower.
Is there a timeframe for the minimum number of cycles?
NC-v4 WEc3:Cooling tower water useposted by Gregory Martin on
I am working on a presentation to educate my office on Lv4. This being a new credit I don't think I am totally understanding the requirements.
Campus Cooling Tower
NC-v4 WEc3:Cooling tower water useposted by Brightworks Sustainability on
My project is not installing a cooling tower, but they will utilize the shared existing campus cooling tower.
No cooling tower
NC-v4 WEc3:Cooling tower water useposted by Maria Porter on
If you have no cooling tower, do you automatically get the point or you are not eligible for the credit?
Dry cooling tower
NC-v4 WEc3:Cooling tower water useposted by Sara Johansson on
Hi, If a project has dry cooling, a type of cooling tower, can it than get this point?
Maximum Number of Cycles
NC-v4 WEc3:Cooling tower water useposted by Apoorv Goyal on
Hi, based on a water test report, if the number of cycles already exceed 10, does that mean that both points are achievable?