C&S ventilation

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Randy Cook  on 

Hello. I'm working on a C&S project and have a question regarding the documentation of the IEQp1 credit. During the design a single tenant was found to occupy the entire site (700k sf).

4
Default Avatar
Senior Project Manager
CodeGreen Solutions
LEEDuser Basic Member
157 thumbs up
Thu Oct 3, 2013, 9:17 am

Ozonation for Lift Lobby Area

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Poorva Keskar  on 

The consultant has proposed an Ozonation System (IAQ Management System) for Lift Lobby area.

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Wed Sep 11, 2013, 10:24 am

ASRS for Warehouse

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Jean-Baptiste Noel  on 

Part of our warehouse project consists of a space (100m*100m*40m) using a ASRS (automated storage and retrieval system). It allows to store goods without people occupying the space.

3
ESD Operations Manager
Green & Global Consulting Pte. Ltd.
LEEDuser Basic Member
4 thumbs up
Tue Mar 26, 2013, 1:26 pm

Lease agreement (signed by tenants)

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Rubén M. R.  on 

I'm working on a mixed-use CS project.

2
Building Performance Analyst
The Green Engineer
LEEDuser Premium Member
11 thumbs up
Tue Sep 11, 2012, 3:34 pm

FTE vs ASHRAE 62.1 occupancy

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Edwin Wealend  on 

Hi All For a C&S project there are default FTE occupancy figures that shoudl be used for water calcs, bicycle racks etc where the final occupancy is not known.

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Thu Jun 28, 2012, 9:49 am

Air Extraction System

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Luis Miguel Diazgranados  on 

We are working on a natural ventilated CS office building. The entire building is going to be natural ventilated with no AC.

3
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Wed Jan 11, 2012, 4:43 pm

Garage and technical rooms

CS-2009 IEQp1:Minimum IAQ Performance
posted by  BH .  on 

We are dealing with project with underground garage, where adjacent spaces are technical rooms. Can we transfer the air from the garage to the technical rooms to ventilate them?

2
Principal, Energy and Engineering Leader
DLR Group | Westlake Reed Leskosky
LEEDuser Expert
267 thumbs up
Wed Nov 30, 2011, 9:11 pm

uncondtioned space and natural ventilation

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Luis Miguel Diazgranados  on 

Hello We are working on a office building applying for LEED CS. The building is going to be naturally ventilated.

2
Principal, Energy and Engineering Leader
DLR Group | Westlake Reed Leskosky
LEEDuser Expert
267 thumbs up
Wed Nov 23, 2011, 4:15 pm

Tenant Layout

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Dan Forino  on 

For our LEED CSv2.0 project, we have been asked to provide a proposed tenant layout for approximately 6 office spaces.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Mon Jul 25, 2011, 5:24 pm

Authority having Jurisdiction

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Diego Prada  on 

We are working on a CS naturally ventilated office Building.