CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Ian McCall on
Hello all, I am working on a large Core and Shell project composed of office spaces and commercial centre (in France). The commercial centre is 5 stories high and occupied by one single tenant.
Tenants Obliged to Share Data with USGBC?
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Ian McCall on
Hello All, Are tenants obliged to share their energy data with USGBC for any period of time?
Process for corrective action
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Maya Karkour on
Hello, One of the requirements of EA Credit 5.2 is to "provide a process for corrective action if the results of the M&V plan indicate that energy savings are not being achieved".
Must be electricity for FCUs ventilators measured?
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Frantisek Macholda on
Hello, we have CS office project. The main HVAC systems are central, there are only fan-coils and small local water heaters in tenant spaces.
Could you explain the plan just one more time?
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Charles Nepps on
I am still a bit unclear about the the M&V - Tenant Submetering documentation.
>75% M&V Template Requirement
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Martin Meehan on
Dear all, Our project recently received the comment below which appears to require an Option B or D 'template' to be submitted with our plan if a tenant is to take 75% or more of the building spa
Metering Requirements
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Ciaran McCabe on
Hi, I am working on a commercial project that consists of retail units on the ground floor and offices on the levels above.Currently the base build does not show and ten ant metering for the retail
Corrective Actions and Sub-metering
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Jatuwat Varodompun on
For the submetering, we can just provide the box that allow the tenant to install the meter, right?
Tenant is installing the entire energy systems at the building
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Michael Wahjudi on
Hi all, we have building where the tenant is installing the entire energy related system (ACMV, lighting, etc). The landlord only provide land and structural of the building.
Single tenant in building pursuing Core & Shell
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Dave Hubka on
The building is pursuing C&S certification and has a perspective tenant that may fit out the entire space.