List energy end uses
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Mike D on
"The M and V Plan omits the table or listing of the project’s energy end uses as required by the form." However, the Plan we have submitted lists the following: Locations and types of energy meter
M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Philip Herriges on
The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools. For NC&
Description of quality assurance procedures.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Rudolph Carneiro on
I recieved a comment for a project of mine and dont really know what they want exactly.
submit to leed-online compliance
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ron Dean on
Good day, i wonder what is the time that I can submit the M&V plan for credit 5.1. May I submit it when the construccion is finished with the rest of the credits for C&S certification or I
EA 5,1
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Muhammad Faisal Azizullah Jaffar on
We are working on a mall project going ahead with the LEED CS GOLD.We are currently on tender stage and the client has suddently come up with the LEED requirement.
EAc5.1 and EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Christos Alexandrou on
Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.
What to measure?
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Marcio Alberto Casado Pereira on
We are working on a multiple building campus, it's a residential project.
M&V plan for cold and dark shell
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Jatuwat Varodompun on
In case the system is yet designed, can CS project get the score in 5.1 and 5.2 by purely using tanant leasing agreement which has the M&V Plan as a reguirement to be responsible by tenants.
Monitoring VRF unit
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Edmée Knight on
We are installing an air cooled VRF system with a DOAS in our building.