I am currently working on an M&V plan for the base building of a Retail Center. After reading further into EAc5.1, I noticed that this credit is separate from tenant spaces. The only actual Landlord areas are a couple of riser rooms, exterior and parking lot lighting. With this scope, would we be eligible for this credit?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Gordon Shymko
PrincipalG. F. Shymko & Associates Inc.
138 thumbs up
August 2, 2010 - 4:18 pm
In general, the M&V program is limited to the base building systems. If the extent of the base building is extremely limited, then the project may fall into the category of "not all projects are eligible for all LEED credits". I suggest a CIR in this particular case.