PRM Modelling Queries

CS-2009 EAc1:Optimize Energy Performance
posted by  Ciaran McCabe  on 

Hi, I have 2 questions in relation to the 90.1 Energy Model. 1) Is Dublin (Ireland) in ASHRAE climate zone 5 or 5a. 2) The building to be modeled is a 5 storey building with a basement.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Jan 22, 2016, 4:38 pm

Baseline Construction Performance

CS-2009 EAc1:Optimize Energy Performance
posted by  Ciaran McCabe  on 

When modelling the Baseline where the building is existing (not a new build) what is the procedure for selecting the baseline constructions in the model. This building is outside the US.

6
Director
Passive Dynamics Sustainability Consultants
LEEDuser Basic Member
12 thumbs up
Wed Dec 16, 2015, 2:39 pm

How does the formula work with mixed new and existing projects?

CS-2009 EAc1:Optimize Energy Performance
posted by  Charles Nepps  on 

Our project building is 75% existing and 25% new construction. When the credit form calculates the EAc1 points, it is done based on a weighted average, which makes sense.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Aug 28, 2015, 3:36 pm

LEED CS 2009 EAc1

CS-2009 EAc1:Optimize Energy Performance
posted by  Ruel Galve  on 

We are currently doing a LEED 2009 CS - GOLD project in Jakarta. The question is: Do we need to select our equipment (pumps and fans) based on the recommended baseline building design power from A

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Aug 26, 2015, 2:04 am

HVAC Systems Selection for Baseline

CS-2009 EAc1:Optimize Energy Performance
posted by  Mark Stromberg  on 

My question is regarding the following procedure as outlined in Trace 700 help: "To determine which ASHRAE baseline system to model, refer to ASHRAE Standard 90.1-2007, Table G3.1.1A (below).

9
Wed Jul 9, 2014, 1:39 am

TABLE 6.5.3.1.1B Fan Power Limitation Pressure Drop Adjustment

CS-2009 EAc1:Optimize Energy Performance
posted by  Mark Stromberg  on 

I would like some help on the intent and definition with some examples that can use 0.5 in. w.c. as credit for: "Return and/or exhaust airflow control devices". Thanks

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Jun 27, 2014, 9:39 pm

LEED Silver with EAp2 only?

CS-2009 EAc1:Optimize Energy Performance
posted by  Matt Humphreys  on 

Is it possible for a project to achieve LEED Silver and only meet EAp2 by demonstrating 10% energy cost savings?

2
Sustainability Director
Lake|Flato Architects
LEEDuser Basic Member
78 thumbs up
Wed Apr 9, 2014, 4:16 pm

Future space

CS-2009 EAc1:Optimize Energy Performance
posted by  Jatuwat Varodompun  on 

In case of project with an area which is already designed but yet built (less than 40% of gross project area), can we use "owner's commitment" instead of "leasing agreement" to state all the design

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Mar 26, 2014, 6:21 am

Clarification on C&S and MEP Systems

CS-2009 EAc1:Optimize Energy Performance
posted by  Emmanuel Gee  on 

Hello, This is our first Core & Shell project and we have a tenant ready for a two story commercial space.

5
President, LEED AP, WELL AP
Entegra Development & Investment, LLC
LEEDuser Premium Member
43 thumbs up
Mon Feb 17, 2014, 4:21 pm

Incorporation of Modulating Exhaust Fan in Model

CS-2009 EAc1:Optimize Energy Performance
posted by  Brian Salazar  on 

Hello again! Our project is in the final throws of appeal and we have been able to secure EAp2 and 4 points for energy efficiency.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Feb 14, 2014, 7:48 pm