DCV requirement for high-occupancy areas
CS-2009 EAp2:Minimum energy performanceposted by Shenhao Li on
Hello! We have a canteen project in Shanghai. The building has three floors, total GFA is 64,067 square feet. The baseline HVAC system type is system 6.
Modeling DCV in open space offices
CS-2009 EAp2:Minimum energy performanceposted by Lucie Cervena on
I am in the process of simulating 7 floor office building. Five of these floors are designed as open space offices, the others are designed as small offices.
Dynamic model compliance analysis results
CS-2009 EAp2:Minimum energy performanceposted by František Bartoš on
Hello, I made model using eQuest 3.65 and after simulation, baseline building generation and results compliance I see 55 % percent improvement in proposed design against the baseline design. This
Area clarification
CS-2009 EAp2:Minimum energy performanceposted by Magda Aghababyan on
Hi, We have Core & Shell project while calculating the area of the locations, Pif and EAp2 have difference approximately 4% please let us know what is the maximum percentage deviation. Thank y
Addenda to ASHRAE standards
CS-2009 EAp2:Minimum energy performanceposted by Jens Apel on
Edit: question has already been answered in February 2012 here: http://www.leeduser.com/credit/CI-2009/EAp2 Didn't find it before, sorry for any confusion. Dear all, on several spots in the Ref Gu
LEED DESv2, System 8 and Chilled Water Temp Reset
CS-2009 EAp2:Minimum energy performanceposted by Matt Humphreys on
For baseline HVAC system #8 modeled with purchased chilled water according to Option 1 of Treatment of District or Campus Thermal Energy in LEED v2 and LEED 2009 guideline, does the Chilled-Water S
Baseline systems for mixed use facility
CS-2009 EAp2:Minimum energy performanceposted by Kim Teachout on
We have a mixed use facility that is 34% hotel, 34% office, and 32% parking garage.
Baseline Ventilation
CS-2009 EAp2:Minimum energy performanceposted by Toni Herena Montull on
Dear all, our previous version of the baseline model in a C&S building had the same ventilation rates than the proposed.
Campus Site Lignting Calcs - again, sorry
CS-2009 EAp2:Minimum energy performanceposted by charles bell on
We submitted (on Jan 23, 2014) the question below. Unfortunately, since then my email has crashed and I have lost the response. Is there any way this can be recovered?
Mandatory provision 6.4.3.2 Setpoint Overlap Restriction
CS-2009 EAp2:Minimum energy performanceposted by Sandra Holmström on
Mandatory provision 6.4.3.2 Setpoint Overlap Restriction When heating and cooling to a zone is controlled by separate thermostatic controls shall heating setpoint exceed cooling setpoint. In our C&