Post a question or comment
Credit Filters
Minimum energy performance
Filter by location
Forum
Topic
Replies
Recent

Core&Shell Process Load on a Manufacturing Facility

CS-2009 EAp2:Minimum energy performance
posted by  Lourdes Salinas  on 

Hi everyone, We have a C&S Major Renovation Manufacturing Facility project. The building is doubling in size and some adjustments will be performed to the envelope of the existing building.

1
Thu Apr 4, 2013, 2:05 pm

How to calculate Process Energy for CS?

CS-2009 EAp2:Minimum energy performance
posted by  Tatjana Ernst  on 

Hi everyone, we have an Core & Shell-Office Building. We are wondering how we have to calculate the process energy.

1
Mon Feb 14, 2011, 1:30 pm

Core and Shell v3 w/ ASHRAE 90.1-2010 w/o tenant agreement

CS-2009 EAp2:Minimum energy performance
posted by  Curtis Clark  on 

We are working on a very large, core and shell project that the owner will not share the tenant agreement with our team. The minimum code requirements are based on IECC 2012/ASHRAE 90.1-2010.

1
Wed Feb 24, 2016, 3:59 pm

diesel generator on-site

CS-2009 EAp2:Minimum energy performance
posted by  Johannes Gellrich  on 

Hi everyone, we are working on a project that produces its electricity on-site via diesel generators.

1
Fri Oct 14, 2011, 9:55 pm

Density Lighting Exterior

CS-2009 EAp2:Minimum energy performance
posted by  gabriel Morales  on 

Hi, we have any questions about the desnsity lighting exterior: 1.- The building is located on a corner in one of the main streets of Mexico City, the architectural design has 23 terraces which wil

1
Thu Mar 15, 2012, 1:08 pm

Precertification requirements

CS-2009 EAp2:Minimum energy performance
posted by  František Bartoš  on 

Hi, is there some document that specifies precertification requirements for EAp2 (eventually for all prerequisites and credits in LEED CS 2009)? Thnaks for advice. Frank

1
Wed Nov 6, 2013, 5:54 pm

lighting requirements

CS-2009 EAp2:Minimum energy performance
posted by  Agnieszka Rylska  on 

And one more thing just to be sure: Does the project need to comply with lighting power allowance requirements of sections 9.5 or 9.6 (ASHRAE 90.1-2007)?

1
Sun Jan 19, 2014, 12:11 am

energy costs

CS-2009 EAp2:Minimum energy performance
posted by  Francesco Passerini  on 

Sometimes in the energy bills a part of the costs doesn't depend on the energy that is used (e.g.

1
Fri Aug 8, 2014, 6:03 pm

EUI for LEED projects

CS-2009 EAp2:Minimum energy performance
posted by  Ron Dean  on 

Please, I would like to know where I can find the Energy Use Intensity (EUI) factors for LEED projects, according to their climate zone (per ASHRAE) and their activity.

1
Fri Apr 26, 2013, 9:56 pm

ASHRAE AEDG Retail - Prescriptive skylight requirement

CS-2009 EAp2:Minimum energy performance
posted by  Alexis Voeltner  on 

We are working on a small retail store 18,000 sqft and we are considering pursuing the prescriptive compliance path AEDG (option 2) to meet EAp2.

1
Fri Sep 4, 2015, 6:31 pm