MERV Filter Replacement
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Sheela I on
Prior to demo/During construction we have installed MERV 8 on the return air units. But after construction the replacement of the filters is managed by the building management.
1
Mon Jun 25, 2012, 7:45 pm
100% Outside Air systems
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Christie Rimes on
The base building HVAC system uses 100% outside air. Therefore there are no return grilles. I am assuming that the requirement for filtration then is not applicable?
2
Thu Sep 10, 2015, 11:37 pm
Pre Occupancy Filter Replacement for a Tenant
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Laura Charlier on
Is a CI project required to replace the filters of the main building AHU? The project is a 5000 sf office space tenant in a 162,000 sf building (no AHU's in the space).
2
Mon Nov 26, 2012, 10:25 pm