Materials Cost - Materials and Resource Calculator
CI-2009 MRc4:Recycled Contentposted by Ricardo Sá on
I have just received the final application review for a LEED CI v2009 project, and under the MRc4 & c5 the LEED reviewers stated: “the Actual Materials Cost for Divisions 3-10, 12, 31, and 32
PDF Template Question
CI-2009 MRc4:Recycled Contentposted by elizabeth warlop on
Hello, I may have a question similar to above. In regards to the costs that get included in table L-3 CSI Divisions 3-10 as well as Table L-4 CSI Division 12.
Furniture Value
CI-2009 MRc4:Recycled Contentposted by severine secret on
When documenting the furniture value of an order for credits MRc4 thru Mrc7, do we include local tax, installation and freight on the total order?
Furniture & Pillows
CI-2009 MRc4:Recycled Contentposted by severine secret on
Do we need to list pillows? or are they considered accessories?
Confidential Materials Cost Budget
CI-2009 MRc4:Recycled Contentposted by samala hartley on
This LEED CI project would like to maintain privacy in regards to their materials budget.
Recycled content " Broadloom Carpet"
CI-2009 MRc4:Recycled Contentposted by michael giannini on
The question i have pertains to the way information is placed on manufacturers websites and the validity of the information posted.
Pre-Owned furniture
CI-2009 MRc4:Recycled Contentposted by Susan Di Giulio on
If a project is using less than 30% of the furniture budget's worth of pre-owned furniture, and thus not attempting MRc3.2, can that be used towards MRc4 instead?
Material Values
CI-2009 MRc4:Recycled Contentposted by Holly Himes on
On the IDC Materials Calculator download from LEED-online states in footnote 2 that material value must "include all expenses to deliver the material to the project site, including taxes and delive
Hand drier
CI-2009 MRc4:Recycled Contentposted by soha yamani on
hand drier installed in toilets : should it be included in materials ? if yes under which CSI division it is mentioned