Forum quick links
Furniture Donations and Reuse
CI-2009 MRc2:Construction Waste Managementposted by Kasey Kudamik on
We have a client that is building out a LEED-CI certified office space in a new location and will move from their current offices after the build out is complete.
MRc2 Construction Waste Management
CI-2009 MRc2:Construction Waste Managementposted by Michael Roth on
I have comingled waste and diverted metals. One recycler sorts CMU, wood, paper/cardboard and metal off-site and records are kept in CYDs. The other two recycle centers do Ferrous metal
Alternative Daily Cover
CI-2009 MRc2:Construction Waste Managementposted by Lawrence Lile on
We are building a maintenance facility at a landfill. It would be very easy to use excavation material as Alternative Daily Cover, as the area that uses this is very close.
CI MRc2 Concrete & Brick
CI-2009 MRc2:Construction Waste Managementposted by Joseph Sneed on
I have a project that has a lot of brick & concrete demolition. This will be used as "clean fill" at a Metrofill site located somewhere else and not taken to a "landfill".
wood
CI-2009 MRc2:Construction Waste Managementposted by Juliana Malho on
Whern you burn a wood that was diverted from landfills, is it considered recycling??
Electronic equipment
CI-2009 MRc2:Construction Waste Managementposted by Agnieszka Rylska on
Should electronic equipment be included in the waste calculations (should we monitor it's weight) or should it be only mentioned in the Construction waste management plan that it's exluded from the
Concrete wash-out water
CI-2009 MRc2:Construction Waste Managementposted by Christine Castellano on
The company we hired to provide concrete washout containers RECYCLES the water, can this water recycling count towards LEED credit - if yes in what category - materials and resources? Thanks
Two Stage CI LEED Assessment?
CI-2009 MRc2:Construction Waste Managementposted by Chris Hocknell on
Dear all, I am submitting a Two Stage LEED Assessment and I am not sure how to deal with credits such as The Site Waste Management Plan.
Separating waste - reuse at household
CI-2009 MRc2:Construction Waste Managementposted by Maria Glädt on
We have a project where there for example lighting fittings, some doors etc. that would be possible to reuse at other in other buildings.