Experiences about ACP Pilot Credit – No Cooling Tower (WEpc94)?

Pilot-Credits WEpc17:Cooling tower water use
posted by  Christina Nybergh  on 

Hi, anyone got any experience with the Alternative Compliance Path WEpc94 – No Cooling Tower?

4
Energy Efficiency Ninja
Grumman/Butkus Associates
LEEDuser Premium Member
64 thumbs up
Wed Jul 11, 2018, 8:38 pm

Sidestream filter?

Pilot-Credits WEpc17:Cooling tower water use
posted by  Jonathan Weiss  on 

The credit requirements do not call for a sidestream filter, but the documentation requirements list that we should confirm that a sidestream filter is being provided. Why is that?

1
Mon Sep 10, 2012, 1:21 pm

Sand Filter

Pilot-Credits WEpc17:Cooling tower water use
posted by  Kenner Kingston  on 

The credit requirement #5 asks for a "diagram showing meter locations, sand filter.: Is a sand filter required to meet the credit?

1
Thu May 16, 2013, 5:37 pm

Pipe Corrosion Rates

Pilot-Credits WEpc17:Cooling tower water use
posted by  Charles Chaloeicheep  on 

How do you determine the predicted acceptable corrosion rates for each pipe material in the condenser water system?

0

2009 for Schools

Pilot-Credits WEpc17:Cooling tower water use
posted by  Dana Murdoch  on 

Can this PC17 be used for LEED 2009 for Schools??

1
Fri Jul 15, 2011, 2:20 am

Providing verification that there will be side stream filtration

Pilot-Credits WEpc17:Cooling tower water use
posted by  Sara Greenwood  on 

Our project is pursuing an ID point for Pilot Credit 17 under the LEED-NCv2009 rating system.

0

Never Have Cooling Towers

Pilot-Credits WEpc17:Cooling tower water use
posted by  Janice Rogers  on 

We do small renovations and have never installed or replaced a cooling tower. Do I still have a "no" credit even if I can't meet the criteria of the credit because we don't have the equipment?

0

One-Time Potable Water Analysis

Pilot-Credits WEpc17:Cooling tower water use
posted by  Edward Malesevich  on 

When the credit requirements ask for a "one-time" potable water analysis to be conducted, what sort of time-frame is required for this to be completed?

1
Wed Mar 13, 2013, 2:28 pm

Cooling tower cycles

Pilot-Credits WEpc17:Cooling tower water use
posted by  Phuc Do  on 

Hi all, Our project is using Munters cooling tower in which the cooling tower cycles measured continuously and the dump cycle adjusted accordingly.

0

How long does the monthly monitoring last for?

Pilot-Credits WEpc17:Cooling tower water use
posted by  William Wong  on 

One of the mentioned requirements is to report results of the amount of potable water used, microbiological levels, blowdown and corrosion on monthly basis, but for how long after occupancy?

1
Tue Feb 8, 2011, 2:24 pm