CI-v4 EAp3:Fundamental refrigerant managementposted by Laura Charlier on
"For existing buildings with existing equipment or projects that use existing central plants, teams will need to check if CFC-based refrigerants are being used.
Fundamental refrigerant management for a "District Energy System"
CI-v4 EAp3:Fundamental refrigerant managementposted by Ralph Bicknese on
To be clear, does the upstream equipment in a District Energy System need to be considered for the prerequisite or only for the enhanced refrigerant management credit? Based on the "project t
Cooling Towers
CI-v4 EAp3:Fundamental refrigerant managementposted by Laura Charlier on
If cooling tower is being replaced as part of project, does that need to be included in calcs?
Existing Chillers in Basement (not in project boundary)
CI-v4 EAp3:Fundamental refrigerant managementposted by Heather Zeto on
Our project is a 4-floor fit-out of a hospital tower (Less than 200,000 SF of an existing 8 Million SF building).
Existing small HVAC&R units
CI-v4 EAp3:Fundamental refrigerant managementposted by Mercedes Ferreira on
For the Fundamental Refrigerant Management credit under the ID+C rating system, when the requirement says, "Existing small HVAC&R units (defined as containing less than 0.5 pound (225 grams) of