18
Mon Apr 21, 2025, 9:33 pm

LEED v4 BD+C, EAc1 Enhanced Cx, Option 2. Envelope Cx: Can General Contractor contract for the BECx testing?

NC-v4 EAc1:Enhanced commissioning
posted by  Theresa Lehman  on 

Has anyone come across a scenario where the general contractor is required to contract for the functional testing of the building envelope commissioning, where the hired BECx simply "observes" the

1
Tue Dec 10, 2024, 3:57 pm

Multiple Cx Agents for the Option Paths

NC-v4 EAc1:Enhanced commissioning
posted by  Saagar Patel  on 

I do commissioning and I work at a design firm.  When a customer pursues both Fundamental and Enhanced cx- my group would not be able to do the Cx of the project.  However, we believe the

4
Tue Oct 8, 2024, 12:57 pm

Enhanced Commissioning - Envelope Commissioning

NC-v4 EAc1:Enhanced commissioning
posted by  Todd Bundren  on 

I am working on a new Cancer Center in St. Louis, MO. We are pursuing the envelope commissioning credits and have a question regarding the requirements:

1
Sat Sep 7, 2024, 6:42 pm

Can MEP CxA be more than 1 person?

NC-v4 EAc1:Enhanced commissioning
posted by  Michael   on 

Hi LEED Experts, I would like to ask: Is it a must to have only 1 key CxA person who will sign all the MEP functional testings?

1
Wed Aug 14, 2024, 12:08 pm

Test and balance

NC-v4 EAc1:Enhanced commissioning
posted by  Heather Holdridge  on 

I understand that there were not any requirements regarding TAB in LEED 2009 -- is this still true for v4?  Just want to confirm that there are no issues with having the balancer contracted un

3
Tue Dec 19, 2023, 10:33 pm

Can the envelope commissioning (to earn the 2 points) be carried out by company of the facade execution?

NC-v4 EAc1:Enhanced commissioning
posted by  Sara BENLOUBA  on 

We have appointed a facade / curtain wall company for our project and we intend to entrust it with the mission of carrying out the necessary tests concerning the commissioning of the envelope.

9
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Thu Jun 1, 2023, 1:44 pm

Deadline for hiring CxA

NC-v4 EAc1:Enhanced commissioning
posted by  Elizabeth Powers  on 

Does anyone know if there is a deadline for hiring the CxA in the v4 credit? I know I'd recommend no later than DD, as that but am unclear if v4 has a hard deadline.

8
Mon Jan 23, 2023, 6:27 pm

Envelope Cx

NC-v4 EAc1:Enhanced commissioning
posted by  jordi casajuana  on 

Dear all, I am CxA and I am trying to include Envelope Cx on my services. However, after a quick glance at the v4 guide, some questions have appeared. Which tests are mandatory to get this Cx?

4
Default Avatar
Commissioning Engineer
CannonDesign
LEEDuser Basic Member
4 thumbs up