Can I recycle stones from excavation?
Schools-2009 MRc2:Construction Waste Managementposted by Blanca Cespedes on
I understand that the intent of this credit is to divert construction and demolition debris from disposal in landfills and incineration facilities.
Waste to energy conversion
Schools-2009 MRc2:Construction Waste Managementposted by Jesse Stockley on
I am trying to select a waste management company. The low bidding company says they have done several leed projects with local contractors.
hardfill
Schools-2009 MRc2:Construction Waste Managementposted by Eri Spaulding on
In one of our projects, most of the construction waste (especifically concrete and masonry) has been used as hardfill in land outside this project, in a location where other construction will take
Wood as a fuel and method of landfill diversion...
Schools-2009 MRc2:Construction Waste Managementposted by Ward Miller on
In general, the country where I am pursuing a LEED for Schools cert. has little to no experience separating waste beyond two groups: steel and mixed construction waste.
Demolition and New Construction as separate phases
Schools-2009 MRc2:Construction Waste Managementposted by Caroline Kilbane on
Does the demolition of an existing building have to be included in the Construction Waste management Plan if it is part of an early Site package which is happening about 8 months before the constru
Demolition of existing building
Schools-2009 MRc2:Construction Waste Managementposted by Matthew Heaton on
I’ve encountered a differing of opinions regarding the Construction Waste management credit (MRc2) and could use some help.