CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Susann Geithner on
Here are some real live applications for IAQ management during construction http://on.fb.me/vboaSs
Wet mineral wool on spandrel
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Antonio Rodriguez on
I am working on an office tower project in Panama, and rain season is about to begin. What should we do if the mineral wool used for insulation on spandrels should get wet?
Exposed duct insulation in open return plenum IAQ concern?
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Greengrade User on
We are trying to achieve LEED CI v2009 Certification. The project is a 6,237 SF office space tenant in a 336,510 SF building occupying approximately 50% of the 11th floor.
Form requires photos of moisture control
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Raphael Sperry on
Has anyone else noticed that the form requires "Upload photos documenting moisture protection methods. Photos should include date and time stamp.
MERV Filter Replacement
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Sheela I on
Prior to demo/During construction we have installed MERV 8 on the return air units. But after construction the replacement of the filters is managed by the building management.
temporary capping of the remaining duct work
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Megan Bove on
If there is a project that is going to demo 1/2 of the ductwork on a floor site hich the building is keeping on the HVAC System during construction do we need to put temporary capping of the remain
IAQ - Visual Documentation
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Gregory Minott on
I am working on an existing government project with restrictions on photography within the building.
Carpet Material ??
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Jan Senica on
We wanted to know if you could please help us out with the carpet material. At the entrance of each door, we are suppose to provide a carpet mat that is suppose to trap dust particles & contain
Cleaning Requirements for bathroom demo
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Megan Bove on
If there is a CI project that has an existing bathroom that is set to be demolished as other build outs are happening, are there specific VOC requirements for the products that they can use?
IAQ Concerns due to LEED boundary
CI-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Kunjan Shah on
My project is inside a 3 story building. The remodel work spans all 3 floors and City permit drawings show work all over the building and building shell.