Furniture Donations and Reuse

CI-2009 MRc2:Construction Waste Management
posted by  Kasey Kudamik  on 

We have a client that is building out a LEED-CI certified office space in a new location and will move from their current offices after the build out is complete.

4
Default Avatar
LEEDuser Expert
472 thumbs up
Fri May 10, 2019, 4:56 pm

MRc2 Construction Waste Management

CI-2009 MRc2:Construction Waste Management
posted by  Michael Roth  on 

I have comingled waste and diverted metals.  One recycler sorts CMU, wood, paper/cardboard and metal off-site and records are kept in CYDs.  The other two recycle centers do Ferrous metal

4
Thu Feb 8, 2018, 9:55 pm

Other uses of Rock Wool Insulations

CI-2009 MRc2:Construction Waste Management
posted by  Katherine Ann Resurreccion  on 

Hi, currently we are having a problem diverting our Rock Wool Insulations for MRc.2.

1
Fri Feb 7, 2014, 1:37 pm

Does Alternative Daily Cover count as Waste Diversion?

CI-2009 MRc2:Construction Waste Management
posted by  JaDee Harsma  on 

We are shooting for 95% waste diversion on our LEED-CI 2009 project.

1
Mon Mar 12, 2012, 7:18 pm

Attempting to return ceiling tiles from demo

CI-2009 MRc2:Construction Waste Management
posted by  Dean Wilson  on 

We are performing a 2009 Commercial Interior for the reuse of a 7000 sq ft decommissioned Army base building. In the demolition phase, we collected old ceiling tiles to return to the manufacturer.

1
Thu Feb 11, 2016, 7:57 pm

Tristan,
Refering to my

CI-2009 MRc2:Construction Waste Management
posted by  Greengrade User  on 

Tristan, Refering to my comment below, the only thing I can think of right now is to seperate the demo process into two parts.

1
Fri Aug 10, 2012, 1:53 pm

Documentation

CI-2009 MRc2:Construction Waste Management
posted by  Jose Ng  on 

We have planned to give the excess material to workers. How can we document it? Best, J.Ng

1
Fri Oct 11, 2013, 3:36 pm

Plaster Recycling

CI-2009 MRc2:Construction Waste Management
posted by  Greengrade User  on 

Hi all, I am working on an interior renovation for a buidling that was built in 1907.

1
Thu Aug 9, 2012, 7:19 pm

Moving Compost

CI-2009 MRc2:Construction Waste Management
posted by  Lawrence Lile  on 

Soil is generally not allowed to be included in waste diversion calculations. But what if we are moving compost?

1
Fri Jun 28, 2013, 1:34 pm

Asphalt Roll Roof Recycling

CI-2009 MRc2:Construction Waste Management
posted by  Sabrina B  on 

I am working on a existing building renovation. The existing roof, which will be demo'd, is asphalt roll with batt insulation underneath.

1
Tue Nov 8, 2011, 7:30 pm